Replacements Underway - two locations
Water main replacement work began today, as posted and per the "official" association website.

Work is proceeding well, but there is a schedule adjustment. Valves have been installed at Dover/Plymouth and Gloucester and the water is 'on.'  There should be no further water interruptions at those two locations. Actual installation of the new water mains at Dover/Plymouth and Gloucester should be completed tomorrow (May 28).

Work at Salisbury may not begin until later in the day on May 28 and may not be completed until Friday May 29. That is a schedule change. 

Plymouth/Dover