Updated Surplus Numbers

Updated Surplus Numbers
Updated Surplus Numbers: Actual surplus 2018 per audit was $85,163.
Boards 2011-2018 implemented policies and procedures with specific goals:
stabilize owner fees, achieve maintenance objectives and achieve annual budget surpluses.
Any surplus was retained by the association.
The board elected in fall 2018 decided to increase owner fees, even in view of a large potential surplus

Average fees prior to 2019

Average fees prior to 2019
Average fees per owner prior to 2019:
RED indicates the consequences had boards continued the fee policies prior to 2010,
BLUE indicates actual fees. These moderated when better policies and financial controls were put in place by boards

Better budgeting could have resulted in lower fees

Better budgeting could have resulted in lower fees
Better budgeting could have resulted in lower fees:
RED line = actual fees enacted by boards,
BLUE line = alternate, fees, ultimately lower with same association income lower had
boards used better financial controls and focused on long term fee stability

Wednesday, August 27, 2014

Response of Management to My Letter of February 14, 2007

1 comments

Bookmark and Share

From my archives. On February 14, 2007 I wrote a letter to management with separate copies mailed to each board member. That letter is the previous post. This is the mailed response by the Director of Management at our HOA management firm:

"March 12, 2007

Dear Mr. [My name]

On behalf of the Board of Directors and management, 1 would like to thank you for your correspondence pertaining lo the financial condition of the Briarcliffe Lakes Manor Homes Condominium Association. Since your correspondence arrived shortly after the February meeting of the Board of Directors, it was placed on the agenda of the March meeting. All of the members of the Board expressed their comments and certainly recognized the thoughtful approach that you have taken.

Your comments are and were echoed by the Board members. Sometimes it is a very close balance between structuring the assessment level while still providing the necessary funding to not only maintain the day-to-day operations of the Association; and, still be able to the fund the long-term needs of the Association for capital repairs. These decisions are always difficult. But you, like the Board of Directors, are concerned about maintaining the value of the properly. They would prefer paying a little more each month than being faced with the much more difficult financial task of paying for a special assessment.

Again, thank you for your thoughtful approach to your correspondence.

[Signed, The Director of Management, with copies to the manager and the board]"


Note:
In 2007 the board was clearly struggling with finances. I find this letter of response somewhat ironic. About 18 months later, when some owners arrived at HOA board meetings in 2008 and assailed the board and management, they said the board was not responsive, controlled communications and was unfair and uncaring.  The above letter is one of the reasons I challenged those owners and that 2008 replacement board.

Tuesday, August 26, 2014

Letter to Management and the Board, February 14, 2007

0 comments

Bookmark and Share


From my archives. Severn years ago, at the time this letter was written I had been an owner for 6 years. I had been monitoring finances since 2000, which was prior to purchase. About 18 months after this letter was written many of the board including the president were replaced. The problem seemed to be owners irritated by fee increases. Over the next two years the new board entrenched its position and attempted to replace management.

"Dear Mr. [manager with separate copy mailed to each board member]

Thanks to you for the work that is done. Thanks also to the board, as a former "volunteer" I understand what that means.

My spouse and I have had the opportunity to "digest" the info presented in the most recent annual meeting and also in subsequent "Manor Briefs". I have some observations to make. I also made a spread sheet and I thought I would share it. [Spreadsheet omitted for this post]

One of the items that is becoming a possible issue is the increases in the monthly assessments. The 2007 budget includes an assessment increase that is 6.0%. Now, that is larger than the CPl but I do understand the forthcoming electricity increases and the maintenance issues that the association faces. Frankly, it is my opinion that the people who lived here for the first 25 years got a bargain, as apparently there was minimal consideration to acquiring reserves for major repairs. Of course this also created a problem as the unit owners became used to the unusually low assessments. I can sympathize with the [owner] who wrote you before the annual meeting and was struggling with the increases and was attempting to find methods to move services from the association to the unit owners, and in so doing, reduce the monthly assessment.

[Paragraph removed for brevity and to preserve confidentiality].

When my spouse and I decided to purchase a unit in Briarcliffe Lakes in February 2001, we were concerned by the amount of the financial reserves. It seems our concerns were well founded, as roof repairs are on the horizon. I am hopeful the assessment increases will prove to be sufficient and special assessments will not be necessary. However, your statements and the statements of board members at the previous annual board meetings were not encouraging. I recall hearing a comment at a board meeting that a roof costs [dollar figure removed]. If so, that is greater than $1.6 million for the entire complex.

On reviewing the published budget, my spouse and I were wondering about the details as they apply to an individual unit owner; a $1 million dollar annual budget is a lot of money. So I made a spread sheet, copy attached. I applied the categories to my "Unit B" monthly assessment. As result I arrived at the following figures for the "Projected Year End 12/31/06":

Monthly assessment = $242.45, distributed as follows:
Monthly Utilities = $14.92
Monthly Maintenance and Repair = $10.56
Monthly Common area Maintenance = $51.42
Monthly Waterfall/Creek Maintenance = $0.63
Monthly Building Maintenance = $76.33
Monthly Administration Expense/Insurance = $42.17
Monthly General Reserves = $46.42

The spread sheet includes a column for annual assessment which is based on the data released in the December 2006 "Manor Briefs". To arrive at the distribution for the General Reserves I applied the unexpended funds on a percentage bases (pro rata) to the various reserve categories. This applies about $2,200 per building per year to the roofing reserves. At that rate, it would normally take 10 years to acquire the necessary funds. Of course, I don't know the amount accumulated to date in General Reserves for this program.

Sorry if this is getting a little long.

I also am aware of the issues concerning renters and parking. I think they are both sourced by changing demographics at Briarcliffe Lakes. My concerns are probably mainstream. As the population ages, there will be increased turnover. New owners seem to have more vehicles, typical of younger families, etc. In my building we have as many as three vehicles for a unit............ In 2001 there were 5 or 6 autos. If that is representative of a trend, then there are serious parking problems on the horizon.

I see a benefit in limiting renters in the complex. I also see problems if this does not come to pass. In my case, in the event of death of me and my spouse, the unit is willed to my sons. I have discussed this with them and I can foresee that in the event of my death, they would be more likely to choose to rent the unit rather than to sell. I wonder how many other, older unit owners (those over 60, like me) are in similar circumstances? This could have a profound impact on the makeup of Briarcliffe Lakes over the next 10 years.

Sincerely,

[My Name]"



Sunday, August 24, 2014

Owners and Boards - Part 2

0 comments


Bookmark and Share

This post is one of several on a broad topic. This post, number 2 in a series, will look at communications, touch upon financial aspects and owner attitudes. It will look at how these are influenced by the board and how boards are influenced by,  or are a reaction to, owners.

How did Owners and Boards Cooperate to Get This HOA Where it Currently Is?
Before proceeding, it is necessary to remind the reader that 1) Owners elect the boards, 2) Boards are comprised of owners, 3) Owners do their best to influence the boards and 4) The current situation at BLMH  was achieved over decades with many elections, by many hundreds of owners and various boards. It required the cooperation of boards and owners to achieve both the positive results and the negative ones.

I also want to point out that any Operations and  Maintenance activities, as well as any Financial Reserves were all achieved by the boards with the support of owners.

Some of the events that resulted in the current situation were determined a decade or more ago; owners were intrinsic to the board decisions over those decades. A variety of boards were elected and they made the many, many decisions that have resulted in this HOA being precisely where it is, at this place and time and with the current financial and maintenance successes and issues. Yes, there have been some failures along the way. However, it is also useful to point out that this HOA has been able to provide most maintenance successfully. It is also useful to point out that are fees are what they are because of a necessity to catch up and save for the current roofing project and driveways.

The many decisions over decades have also shaped owner attitude. However, board members are owners who were elected to a board position by owners. The exceptions have been appointees, who filled a place vacated by leaving board members or never filled via elections. These appointees were also owners, and boards are inclined to select appointees who will be compliant with the board.  In summary, I suggest that the boards have been nothing more than a reflection of owner attitudes. The owners are ultimately responsible for the outcome, and if is may seem to be too good to be true (low fees = well maintained property), well, as the saying goes "If is seems too good to be true, it probably is."

The relationship of boards and owners is synergistic, and it can have both positive and negative aspects. Should boards operate as owners? No, they are fiduciaries and are held to a higher standard. However, it is also true that many board members fill a position for only a a year or so. They then return to the ranks of the other owners, and as several board members have stated about some of the other owners "These are my friends and neighbors." So board members are certainly caught between operating as fiduciaries which is to say, operating for the good of the entire association which I mean to be all present and future owners, or operating as an owner, and in accordance with their personal whims, wishes and complaints, or those of their close circle of "friends and neighbors." By deduction, I have the opinion that over the years a variety of board members have operated for themselves and for, or under the advice, of a variety of small groups here at BLMH.

Some years ago I made the decision to avoid such entanglements. One must choose between popularity and fiduciary. It's not an easy decision and there are consequences. Based upon my experiences here at BLMH, I have come to some conclusions and I have made other decisions. Those will be in future posts.

Shaped by Decades
Our finances and the condition of infrastructure have been shaped by decades of owner and board decisions. It takes 15-20 years to save sufficient funds for streets, driveways and roofs. It can take longer for garages, entrances and tree replacement. If savings are insufficient for a decade or more the resulting reserve shortfalls or maintenance lapses will result in higher fees for years. Another consequence  is a flurry of activity when reserves finally become sufficient to accomplish needed maintenance. I've written at length about the consequences of a "kick the can down the road" approach in HOAs. However, I would say it is the most recent 5 years that can have the greatest impact on the present situation. Nevertheless, the decisions made today will also impact the situation 5-10 years hence.

Have Various Boards Attempted to Influence Owner Attitudes?
I would say they have, but with varying degrees of success. The primary means of communications is the Newsletter. This is augmented by letters and other mailed correspondence. Owners who attend HOA meetings will be made aware of much of the content of the "Management Packet" and I do provide management and the board with an additional monthly report spanning 4 to 12 pages and one or more spreadsheets. The contents are discussed before the owners. The exception is sensitive issues which cannot be discussed outside of executive session; e.g. who is delinquent, who is foreclosing, who is suing us, etc.

What's been done to better involve owners? The content and character of the BLMH newsletter has changed dramatically in four years. It took a lot of hard work to do this. Believe me, no board member wants to write this stuff, which can be time consuming. Creating meaningful reports, spreadsheets and charts are also very time consuming. So too is taking photos, editing and cropping them and inserting them into the newsletter. Each newsletter also has to be formatted, and my articles are edited to fit within the available space. When other board members send in a long article or articles mine is edited and shortened. A breakdown occurs when a board member or management submits an article after the newsletter has been completed, or after telling me "the article is in the mail" it never arrives. I then get to rearrange everything. The reader may notice white spaces in the newsletter from time to time. It was supposed to be occupied by someone's article. I simply move things to spread that space out. At other times the newsletter is filled completely with text. It's reasonable to assume that my article was shortened to fit the space and has been edited.

Informing Owners
I think most owners would prefer to be informed, but it is true that a very few have complained about the content of the newsletters. The complaints have diminished. Perhaps the complainers simply gave up. A few owners have no tolerance for "bad news" or what they construe to be "less than cheerful" news. I suspect that has been one of the impediments to a more informational newsletter. Not everyone on the current board is enthusiastic or in agreement about the current newsletter.

Of course, bad news isn't easy to handle. Here's a question. Would boards sometimes gloss over uncomfortable facts? Would boards avoid giving "bad news" to owners, and why could that be? For example, could a board or boards be inclined to avoid communicating long term financial issues, statistics about delinquencies and foreclosures, or avoid dealing with other HOA problems such as rules violations? I assert that's why newsletters from time to time look like a "feel good" doily taken from a restaurant. It's not what is said in the newsletter that has been disturbing to me. It's what is unsaid that is the problem.

I do realize that there are differences of opinions about what should be published in a public newsletter. Fine, then let's discuss and provide that information to the owners who attend HOA meetings, or send it via a letter. That too seems to be a problem and one prevailing argument is the cost of postage to the HOA.

On reading the newsletters and other correspondence over the years, I'd say a variety of boards did their best to avoid providing bad news, or avoided news that might put the board or the HOA in a bad light.  I've attended many HOA meetings and I have observed such avoidance by boards. The "Great Recession" began in 2007. Discussing delinquencies, foreclosures and so on was steadfastly avoided while owners were present. Some board members seemed to think all such information including statistics was privileged, and at least one told an owner just that.  Even today, there seems to be a tendency on the part of various board members to avoid this.  Other "bad news" topics include reserve shortfalls,  "bad debt",  lawsuits and legal judgments. Of course, if one doesn't have this information available then statistics beyond the most recent financial report data is impossible. Problem solved!

In terms of finances, there has been an emphasis over the years on the current total saved. There is no question owners do feel better and more secure knowing we have larger balances. However, the bank balances are misleading. To determine if that balance is sufficient also requires knowledge of expenses and in particular, long term expenses. Reserve funds accumulated must be compared to reserves required. Otherwise, erroneous conclusions can be reached. a few years ago I enrolled a few concerned owners here at BLMH and a letter was composed and sent to each and every owner, at our personal expense. That letter provided a realistic view of the financial situation. The next post in this series will look more closely at reserves and long term finances.

Communicating Financial Status
In a HOA there are financial assets, but there are also financial liabilities. Using the "Balance Sheet" is an inadequate indicator of financial health for a HOA. The funds saved as reserves will be offset by the costs to maintain the infrastructure we are saving for. Those costs will occur in the future and our HOA is required to build adequate reserves. The determination of adequacy is the ability to fund all known capital items for the next 30 years. Balance sheets do not provide that information. I have concluded that owners and some board members look at the reserve balances, see a large number, and are inclined to assume they are adequate. Unless opposing costs are also provided, we have absolutely no idea if the numbers in the balance sheet are adequate or not.

In 2010 I and a few owners did provide a simple analysis of only two components of our reserves via letter to each of the owners. That information was generated with no board or management involvement. It is possible and that letter was a wake-up call.  I do think these things need to be consistently communicated. Not all board members have agreed with me. I have consistently taken the position that:
  1. The balance sheet is an inadequate measure of financial health for a HOA. I was once undecided (2008-9) but on reflection and analysis I decided that quality reserve studies are a necessity and should be updated with regularity. 
  2. Providing data and providing information are not one and the same. I am of the opinion that most owners will appreciate quality information. A few won't but the well being of all of the shareholders and the association is paramount. 
  3. It is a duty and responsibility of boards to determine realistic costs, set realistic budgets to achieve a savings (reserves) to pay for these costs, and to design fee structures to accomplish this. It is also their duty to communicate this to the owners. Telling owners "We have sufficient funds" or "We have enough money" without providing substantiating documents is insufficient. 
  4. Quality information requires not only telling owners how much we have saved and are saving, it also requires that we, as board members, provide statistics about the HOA status to achieve financial targets, both immediate as well as medium and long term. 
  5. Boards should also provide the owners with information of the current status of targets for reserves. The question to be answered is this: at the current rate of accumulation, will this HOA be able to replace the capital items (roofs, streets, driveways, entrances, patios, garage floors and decks and so on?). If not "at the end of service life" then when? Some boards and board members take the position "never." That's one way to keep fees "as low as possible" for current owners. Such an approach is unacceptable to me, and has put me at odds with some board members, both past and present. 
  6. It is important to be aware of the answer to these questions: Will such replacement occur in accordance with a timely schedule based on realistic projects of the remaining life? Do the current reserves and realistic, projected, future expenditures agree, or will there be a shortfall or overage?
  7. Boards should provide owners with both the current state of reserve savings and the projected costs of the infrastructure to be replaced using those funds.
  8. In the absence of quality information, elections become at best popularity contests and at worst crap shoots. Some owners will always vote for whomever promises the lowest fees. 
  9. It is important to be aware of what is not included in future projections. For example, are entrances included or do we expect those doors and foyers to last forever? Anything not included in reserve calculations will be replaced via the annual Operating and Maintenance budgets. A failure of boards to plan and prepare for this will result in higher fees or special assessments. For example, we can ignore the condition of garage floors, but at some future date replacement will be required. 
Some owners won't like what is revealed. They may move to replace the board and that is certainly their right. However, boards are held to a higher standard and must operate as such, no matter what! In other words, it is entirely within the right of owners to fire any "bad news" board and to elect "good news" boards. There is no confusion about our status as individual owners. Owners may do as they please as long as they uphold the rules. One of the rules is "Pay your fees." 

I assert this type of financial planning is a necessity and aspects should be communicated to owners, including:  percent completion of projects, percent remaining, the time (years) required to complete, the remaining life of the infrastructure before completion is mandatory, the amount of reserves collected per category, the amount remaining to be collected per reserve category and finally, project reserve shortfall or excess.

Of course, it remains to be seen who is to provide this information. With a board 20% understaffed, it could be argued there is no one to do this. Or should we simply add it to the tasks of the Treasurer or Architectural & Maintenance Director?


Information Reality 
Do our owners get this quality information? They do get quite a lot and more each passing year. So why is this a gradual change? There are a range of reasons and it is because of the owners and the character, make-up and capabilities of boards since 2007, and earlier:
  1. Boards may not have this quality information available. Some have never done the necessary work to produce this information. It has to be generated by someone. This HOA did not have a quality, unbiased reserve study until 2011. That was the decision of many boards. 
  2. Boards may not have the tools and skills. I have an office, four printers including a duplexing high speed color laser printer, copier, scanners, multiple computers, mobile hot spot, landline based high speed internet, digital cameras and video equipment, digital projection equipment, all kinds of software tools including video, graphic, spreadsheet, publishing, wordprocessing, project management, CAD, etc. I also have the skills to use them. That is not certainly the normal for a volunteer board. 
  3. Our board is and has been chronically understaffed for years. By chronic, I mean 20% or higher vacancy with no committee members to support such financial activities. At best, three board members have been involved in these financial types of financial activities, and that was in addition to their other volunteer duties. At worst, none were involved and most times only one board member was involved. The duties of a treasurer goes beyond signing checks. 
  4. The requirement to provide this information may be more than a board considers to be normally required.
  5. Some board members may think owners don't care, so why take the time.
  6. Some board members really don't know this information, don't ask, won't spend the money to get it and refuse to generate it. . 
  7. There may be a concern of a "run on the bank" as owners may choose to leave the HOA in the face of bad news, if it were provided. 
  8. Board members are volunteers. There are real limits to the amount of time a volunteer should be required to spend on running this HOA. In light of that, boards do deal with things on a priority basis. 
  9. Boards may be reluctant to provide this information. 
Avoiding Uncomfortable Questions
Owners do have the right to ask the uncomfortable questions. Most don't. For it's part, boards may be hesitant to communicate uncomfortable issues to the owner body. Why would that be? From my experience observing a variety of boards for about 10 years, it is because:
  1. Boards are comprised of owners. We each bring our skills and limitations with us. 
  2. Some owners, on achieving a seat on the board feel it is their duty to operate so as to maintain their popularity. 
  3. Boards are elected representatives, and elections are sometimes based on popular agendas. There is a tendency for boards to tell owners what they want to hear; a failure to do so can result in dismissal as owners put in place more "suitable" individuals. 
  4. A board failure to achieve objectives may also result in owner criticism such as "How could this happen" and "How could you allow this to happen?" We all want to look good, don't we?  To achieve this some boards will gloss over things that might be detrimental to their image. The attitude is "These problems can be solved later by someone else, can't they?" 
  5. Owners do express interest in sales and property values. As fiduciaries, boards may do things to put the HOA in the best possible light. 
  6. Board members are owners too, and as several board members have said about their relationship with other owners "We are all neighbors" or "These are my friends." That may make it very difficult for a board member to be really forthright with owners about unpopular issues. How would your friends feel if they discovered you weren't minding the store and the delinquencies were now in the tens of thousands of dollars? Or it was necessary to raise fees? Would they feel let down, or even betrayed? 
  7. Board members are required as fiduciaries to deal forcefully with delinquencies and rule violations. It's their job to keep the fees rolling in; however, a variety of board members have also stated "We're all neighbors." So how to press our neighbors to pay their fees?
  8. So too with rules. How to enforce them with our "friends and neighbors?"
  9. Board members are owners too, and may have a legitimate concern about the financial health of the HOA. Our property values are also at stake here. As board members, the board has the benefit of professional counsel and should be more aware of a variety of issues, both short and long term. However, boards may or may not share that information with the owner body. 
  10. Board members may be operating as fiduciaries and altruistically. They may want to be "of service" but how that is accomplished is subject to interpretation and is also based on ability and work ethic.
  11. Board members may have a legitimate concern about the financial health and physical condition of the HOA. Dealing with these concerns may take years, and the only way to deal with them and have a real impact on the outcome is as a board member. 
  12. The only way to be instrumental in shaping a HOA is to be a member of the board. In other words, to play the game one has to be on the field. For that reason some board members may be inclined to do whatever is necessary to achieve a board position and to stay there for as long as possible. However, as individuals, board members may have their own agenda.
  13. Board members may be distrustful of some owners and some sub-groups. 

Part 3 of this post will look at reserves and certain financial realities.

Friday, August 22, 2014

Owners and Boards - Part 1

0 comments


Bookmark and Share

One reader disagreed with this statement: "Most of the owners at BLMH apparently think they live in an apartment complex...." The reader asked "Why does this keep coming up and who has been telling you that this is their opinion? and the reader went on to say"Most people move into a condo so that they can build equity in something instead of paying rent each month."

Before I respond to this multi-part comment I think it's useful to consider the role of owners and boards in creating the culture of a HOA. This post will provide a foundation.  Another will look more closely at the role of the boards, and at the issue and consequences of "owners who pretend they are tenants." I assert this misconception does exist. I also assert there are real consequences for a HOA.

Before proceeding, I do need to state here that this series of posts is not about secrets, hidden agendas or a lack of transparency. If you should read into this series of posts that there exists some dark secret at BLMH then it is my opinion that you are mistaken.

A reader recently commented "I think there's a bright future ahead for this association." That could become reality and that opinion is worth exploring. However, that's for another post, and I caution the reader that if they expect wonderful things in the future, it will require that the owners put into place those things necessary to accomplish such a future. That includes "sweat equity", paying fees and building sufficient reserves for a "bright future."  I assert this is becoming more difficult. I state so because of aging infrastructure, an aging population and delinquencies and foreclosures. Is a "bright future" impossible to achieve? Not at all. However, I would say that under the operational structure (the roles of owners and board members) that has existed in the time I have been an owner here that such a wonderful outcome is unlikely.

That reader also commented "It used to be a lot worse. The major issues Norm had were with the old 2008-2010 board. They ran on a hope and change platform."

I also think it's useful to point out that BLMH is a really unique property in Wheaton, Illinois. With that uniqueness comes costs, and unique problems that require unusual solutions and an incredible amount of attention to detail. It is disappointing to me that after 36 years, there remains significant resistance to fixing some problems that have plagued this HOA for it's entire existence. Does that make sense? How is it that this HOA hasn't found the will do deal with some of these things?

So what about the future?
The future will be better or worse or we'll get another "hope and change" board. Whichever, it will be determined by all of the owners. It is the owners who elect the boards and a very few owners occupy the seats on the boards. Other owners may occupy any committee seats, and it is owners who influence the board. In the end, all of the people of power at BLMH are owners. Not everyone remembers this, and a few prefer to deny it or pretend otherwise.  However, my perspective on the future will be the subject of a another post. The involvement and the attitude of owners is critical to the success of any HOA, and that is why I am writing this particular series of posts. It was but 6 years ago that the banks were failing and the "change" board assumed power.

Boards and Owner Misconceptions
What role do boards play in creating misconceptions? In my experience, boards are not always forthright. My opinion might seem to be counter to popular notion. On the other hand, going back about 7 years, there has been a small group at BLMH which complained about a "lack of transparency" on the part of a variety of boards.

That group also seemed to be comprised of "good news" junkies. I found it to be ironic that they demanded good news and transparency. That is not always possible. Such a group can be manipulated:
  1. They will vote for anyone who promises that things will turn out as expected or demanded.
  2. The will vote for anyone who promises that such outcomes require nothing on their part, as owners. 
  3. They will vote for anyone who promises lower fees, 
  4. They will vote for anyone who tells them it is all about board change.
The misconception for such owners is "We, the owners, are just fine and any problems are to be dealt with by someone else." In other words, all I have to do is pay my monthly fee and follow the rules. Everyone else will do likewise and it will all turn out "wonderful."

The owners at BLMH have achieved exactly what they desired via the election process which has occurred each and every year for about 36 years.  Where BLMH is today is not an accident. The fees collected were necessary and at times were insufficient. I've written at length about the problems of a "kick the can down the road" approach. The problems and consequences are real.

The current owners of BLMH pay for the consequences of oversight by boards they and previous owners have elected each and every year, for 36 or so years.

Part 2
Part 2 of this series will look more closely at the role of boards and owners in promoting certain misconceptions, and why they do so.

Tuesday, August 19, 2014

Summary of Board Duties and Responsibilities

1 comments

Bookmark and Share



Briarcliffe Lakes Manor Homes is an incorporated not-for-profit, under the laws of the State of Illinois.
All of the board members should become very familiar with the covenants and other governing documents of this HOA. These documents include:
a.    Bylaws.
b.   Rules and Regulations.
c.    Declarations and Covenants.
d.   Illinois Condominium Property Act.

I.                                     Being a member of the board:
This association is a business. Board members are volunteers, without pay or any compensation. To be a member means “being of service” to others, and putting in the necessary time; however, this is not an “open ended” agreement. But in a case of unforeseen circumstances, it may require more time than expected.
Each member will have specific duties and responsibilities; become clear what they are. If you have specific issues, ask the manager and discuss with the board. Ask questions and engage in an open dialog and inquiry about running the association. Be open and honest with the other members of the board. 
When the opportunity presents itself, get to know the professionals, and that includes the management company, the landscaper, the maintenance company and the attorney, etc. The more you learn about your job and your professional support team, the better able you will be to perform it, and support the others on the board in doing their job.
In today’s world, you should have daily access to a personal computer, printer and email, which may be as important as a telephone.
Become familiar with BLMH as a Private Urban Development, or PUD. Get to know the grounds and the buildings. Each board member is provided with a map of the grounds detailing each street and building, and also each pond and stream. Walk the grounds frequently and get to know this place. The board of the association is only as strong as its weakest link. Everyone on the board should be looking for rules violations, maintenance issues, etc.
Board members have a larger responsibility. If you aren’t ready to take on that responsibility, then you should not be on the board. An alternative is to be a committee member, which does not have fiduciary responsibilities and usually has very narrow and specific duties and responsibilities.  For more on the “Powers and Duties” of the board of Managers, see the Illinois Condominium Act Sec. 18.4.
II.                                          Know your specific duties and assignments:
Be aware of your job duties and responsibilities, and those of the other members of the board. The duties may be unequally distributed, but each member of the board is responsible for the decisions of the board.  
Failure of board members to understand your specific duties and obligations may do a disservice to the association.
Avoid priority conflicts on the board. Each board member must have a basic understanding of their particular role and how it fits into the organization.
Assignment gaps or overlap can create conflicts or confusion, so if possible, members should consider methods to resolve and avoid these types of problems.
III.                                          Be Prepared:
Study the finances including budgets and the reserve study. Ask questions if you don’t understand something. Keep notes, so you don’t ask the same questions time and time again.
Before each meeting, read the materials contained in the information packet provided by management. Read the reports prepared by other members of the board. Read the agenda for the month. Become familiar with these materials before the meeting so you are prepared to discuss the issues and make sound decisions. Make a list of questions. Each member votes; with that power comes responsibility. It is necessary to make informed decisions, using common sense and sound judgment.
If you decide to cast a “no” vote, you can request that your name be attached to it in the official association meeting notes. This is sometimes prudent, but is usually not required.
It is your ultimate goal to become expert on many aspects of the operations of the association, including the buildings and the grounds. That means you must learn the physical characteristics of the buildings; the roofs, masonry, patios and decks. Learn about what is necessary to maintain these buildings, the grounds, streams and landscaping. Become familiar with the various contracts, including snow plowing, etc. and drainage issues, the streets and driveways. The association will only be run as well as the board is capable of running it.
IV.                                          Be a fiduciary:
All members of the board are fiduciaries, or stewards, for the entire association. What does that mean? Board members must act in “good faith” at all times, and avoid favoritism, and must treat all owners identically. The Illinois Condominium Act prohibits the creation of “subgroups” of owners in the association.
Being a fiduciary means that a board member wears two “hats.” One as owner and one as a board member. Don’t confuse them. Your role on the board takes precedent, for the betterment of the association. It requires that you use your best business judgment. This judgment best applies to the facts before the board, protecting the fiscal (monetary) and structural integrity and security of the buildings, the grounds, and the association, and the well-being of the residents. As a fiduciary, the collective interests of the association comes first, and are most important. The interests of individuals come second.
To be a fiduciary also means using common sense, and good business judgment.
All board members when operating in a fiduciary capacity are entrusted with the operation of the association. They are to do what's in the association's best interest, which means making decisions on the merits. It’s not appropriate to make decisions because you have something to gain, a personal agenda, or animosity toward another, or have a concern for another.
As a fiduciary, it’s necessary to respect the confidentiality of the association, and various owners. Being on the board means that you will be privy to certain private matters. Certain facts and discussions are not to be disclosed to others. Discussions between the board and the attorney may be confidential. Discussions in executive session are confidential. Certain matters, those that the board decides are “confidential” are not to be discussed with others, including owners, contractors and vendors.
Attorneys talk about exercising “good faith” as a fiduciary. That means using good judgment, listening to qualified professionals, avoiding conflicts of interest, and always putting the interests of the association before your own, or your “personal beliefs.”
V.                                          Avoid conflicts of interest:
All members of the board must avoid conflicts of interest. If there is a possibility that such conflict might exist, the member must discuss this with the board. Conflicts might include business dealings and relationships, and financial encumbrances which could compromise the directors ability to make impartial decisions. In such situations, the member should recuse themselves from discussion and voting, or if extreme, may be requested to resign.
Never accept gifts or favors or any form of gratuity. Never accept any gift from a vendor or contractor.
Avoid situations with contractors, vendors or owners who are intent upon influencing the direction or the decision of the board.
VI.                                          Be a working member of the board:
Learn your duties and responsibilities. Do your work, your duties and assignments. Avoid unilateral action. Discuss the business of the board only at board meetings and avoid “ad hoc” meetings. The board is to speak with one voice, as a consensus. It is okay to debate the merits of any issue. However, once that issue is decided, it is the duty of board members to support it, even if an individual member disagrees with the decision. The only possible exception is in matters as a fiduciary. In such conflicts, this can be discussed with the professional manager or the attorney. If the professionals consider the board has avoided its fiduciary duty, that is an acceptable time to “take a stand.”
Attend workshops provided by the association where there are special issues to consider, such as budgeting. Consider attending seminars and gaining knowledge and skills.
VII.                                          Be professional:
Being on the board is “leading by example.” Others should be treated respectfully. Treat the professionals as knowledgeable partners. Treat the other members of the board as co-workers. Avoid making inflammatory statements, and defaming anyone, be they others on the board, owners or professionals including contractors and vendors.
If there are problems to be dealt with, plan and prepare to provide solutions.
VIII.                                          Be Realistic:
It’s true, this association is run by volunteers. That means, each member of the board has time conflicts and is dealing with the duality of being an owner and being a fiduciary. The best you can do is realize that this exists, and operate within these boundaries. By being aware “what is so” for yourself and for others, it is possible to do the best possible job on the board. If we choose to pretend there are no limitations, or that we are professionals, and bow to that arrogance, we are prone to less than optimal achievement.
IX.                                          Maintain the purpose and confidentiality of executive sessions and board meetings:
Only certain, confidential matters are to be discussed in executive session. The association board meetings are required to be open to all homeowners.  (A meeting is an assembly of a “quorum” of the board; “workshops” are a possible exception).
The Illinois Condominium Act Sec. 18 (a) 9 specifies that certain portions of the board meetings be closed to the ownership. This is called “executive” session.  This session requires that the board meet behind closed doors and out of view or hearing of the owners, unless a specific owner is involved and invited to attend. The purpose is to discuss specific topics that must be kept private and confidential.  Any “vote on these matters shall be taken at a meeting or portion thereof open to any unit owner.” These sessions must not be used by the board to meet in private and avoid the presence of homeowners.  
During “executive session” typical authentic topics include litigation involving the association, information involving hiring or firing of an “employee, ” discussions of violations of the governing documents (such as Rules and Regulations) or “a unit owner’s unit owner's unpaid share of common expenses,” and related consultation with the attorney or management.
To enter “executive session” a motion is made stating the purpose of the session. This is to be documented in the notes of the open meeting. However, whatever occurs in the closed session is to be kept in separate notes, which are not available for inspection by the owners.
Once in “executive session” the board, with management, are not supposed to discuss any topics other than those clearly stated in the purpose of the motion.
Once “executive session” is over, the doors are opened and owners are admitted. At that time, the open meeting is reconvened and the board votes publicly on all decisions made during the “executive session.” Only with an open vote are the closed session decisions made effective.


1.             Examples of Fiduciary Duties
Example 1:
The board is conducting budget workshops and is discussing fee increases or special assessments. These discussions are decided to be confidential. Members of the board may not discuss these matters with other owners, tenants, former board members, etc.
Example 2:
There is a rules violation, and the board has two points of view on how to deal with this. Some owners side with the violator. However, the board decides to uphold the rules and cites the owner as a violation. As a fiduciary, your first duty is to the association, and after the decision to uphold, you should do so. 
Example 3:
The association is looking for a unit to purchase. You are aware of one, for a very good price. So you purchase it for yourself. You have breached your fiduciary duty to the association.  What should you have done? You should have told the board and management of the availability, so the board could decide. Only after the board voted not to purchase, would you be free of your fiduciary duty so you could purchase it for yourself.
Example 4:
Failing to pass proper budgets, treating some owners differently (for example, providing leniency on fees and assessments to some owners, while failing to do so for others),.
Example 5:
Failing to uniformly uphold the rules.
2.             Examples of conflicts of interest:
Example 1:
A vendor agrees to attend a “meet the board” coffee for the association. That vendor agrees to provide coffee and cake for the meeting. This cannot be accepted.
Example 2:
You have a relative in the contracting business, and that relative wants to be a bidder for some of the business in the association, and approaches the management company. You must announce that this is a relative who will be bidding. You should also not take part in any discussion of this project, bids and the award of contract, to the extent of leaving the room during any of these proceedings. Avoid any possibility or suspicion of unethical bid practices, including viewing competitor’s bids. Any meeting notes should include a statement that you have recused yourself from these discussions and these portions of the meetings.
Example 3:

The association is considering a special assessment. You however, have been cut back in your hours of employment and are concerned that you might not be able to financially handle such an assessment. You should announce to the board that you have personal issues, and cannot participate in this discussion. You should recuse yourself from the discussions, and abstain from any vote.


Notes:

  1. 1. The above was prepared by me in June 2011. The board of BLMH has been reticent to use the above. Now, I ask the reader, is that a good thing or a bad thing for a HOA?  Why would a board or a variety of boards decide that the above isn't something to promote? I can guess why. For one thing, if candidates realized that it was a job and they were fiduciaries, could not run their personal agenda or that of their friends, or to be on the board for the sole purpose of reporting back to the "club" and voting that agenda, well, that would reduce the field of candidates, wouldn't it?  I have learned from hard and practical experience that boards are eager and willing to put anyone in a seat. Boards are at times desperate for help. If a bad apple shows up, and things get ugly, well we can then delegate to management or to someone like me to clean up the messes created by dysfunctional or incapable board members. It's not that easy. Getting someone off the board who is dysfunctional, even someone who is going through a "deed in lieu" (which is a form of foreclosure) can be very difficult if management has been gagged, and the rest of the board wants to take care of the individual. I know, I've been there and seen the "good people" in action (gag). In some situations, the board simply refuses to deal with the mess. That's the way it has been from 2009-2013. What a terrible way to run a business! But then, it's your money we're spending isn't it? As a board stated back in 2009 when things got ugly "I guess we don't look very good." But nevermind. One can always run for the board and ignore their fiduciary duties. Integrity? What the heck is that? If things really get difficult, simply resign and spread malicious gossip aka "libel and slander." I know, because in 2011 I hired an attorney to deal with this, at my personal expense.
  2. 2. For anyone on the HOA board, the issue is how to get through the next year or two with delinquents who revel at shooting at you, or retirees who want their fees reduced, or anyone who purchased at the top of the real estate bubble and now feels trapped. Ditto for those who thought they would sell and move on to somewhere else with a nice retirement nest egg. Now we have more than a few who feel our fees are "too high", broken fireplaces, failing infrastructure and upset neighbors on the other side of lake #4. So what is a board member to do? Let me see, should we be honest about the problems, or downplay them in an attempt to lure some unsuspecting individual to join our ranks?
  3. 3. Most of the owners at BLMH apparently think they live in an apartment complex, and so this post is completely irrelevant.
  4. 4. Oh, and I just sat at my computer and wrote this document, just like the tens of thousands of words I've written, or the many spread sheets I've created for this HOA. What a hobby!

Friday, August 15, 2014

Lakecliffe - Conclusion

2 comments

Bookmark and Share


The Source of Empowerment
What if we each decided that we really, really live here because we choose to, instead of because we have to? That's the source of my personal power. I do what I do because i can, because I choose to and because I want this place, wherever I am, to be a better place and a reflection of choice, rather than something else. It appears this is not the will of the majority. So it is what it is. They will pay the commensurate fees.

I made a choice in 2008 and I decided to make it a demonstration. I have succeeded. What others make of this, or where they take it, that's entirely their personal business. Life is both a choice and an opportunity. What little I have accomplished is a gift. Use it well.

Status
The portion of the street that was repaved is about 99% complete. Signs and equipment have been removed, and there is a section of curb to be replaced, some additional landscaping and that's it. Currently the board is awaiting a review of the material quantities used and so on. This is all "backoffice" stuff and so most of the owners or other residents are unawares, or have no interest.

Problems
One of the problems encountered during the project was the unwillingness of a few residents to comply with notices that were posted, "ROAD CLOSED" signs and so on. To deal with this the construction crews had to dodge vehicles, there was one accident, and I spent numerous hours moving barricades back into position after some @ssholes moved them aside so he/she could drive in.

Bad News
The portion of the street that was replaced represents about 17.5% of the streets in BLMH. In other words, within 5 years the remaining streets will have to be replaced, at a major expense. Some of the base will have to be removed and that would not be required if the streets were properly installed in 2002-2004.

Can street replacement be avoided? No, but it can be delayed. There are two methods available. The most recent, by that infamous board of 2008-2010 was to put their head in the sand and attempt to cut fees, passing the problems and the costs to us, here in the present. The other approach, which I advocate, is to perform preventative maintenance, thereby extending the life of the current streets in a responsible way. That approach will result in the lowest possible annual maintenance costs.

Am I confident the second approach will occur? Not at all. Last night, during an association meeting, while discussing establishing a schedule for carpet replacement, a board member actually made this statement in defense of not establishing a schedule: "In the past, we only replaced carpeting when it became a trip hazard." My retort was "Yes, exactly like Lakecliffe."  That's the really bad news for this HOA. That attitude remains a prevalent one for some owners and some board members. So we will persist in pushing the problems down the road until they become unavoidable and until the costs escalate. Then we can deal with them as "emergencies" and make the really costly decisions. "Penny wise and pound foolish."

The Good News
This is a preliminary estimate, but it seems that the amount of material used was less than that budgeted, and so the cost for that portion of the street replacement should also be lower than that budgeted. However, on ripping up the street it became obvious that the grates for the basins were in poor condition and so all were replaced. That will be at additional cost. On the other hand, we could rip these up one at a time using our maintenance contractor. This would embed the costs in our annual fees, create more seams to allow water in to erode the base and probably cost more in the long run. So what would you have done?

We also got some other good news. If we were today to make the decision to get this street replacement done in 2014, the costs would be about $30,000 more than we are spending. That's about $90 out of the pocket of each owner. In other words, there is a benefit to planning and preparing.

Looking Ahead
The new portion of the street, with preventative maintenance, primarily crack filling, will be here and in good service for 20 years. When it is necessary to replace it, only the asphalt will be stripped, reducing the replacement cost by 50%.

The Really Bad News
This is comprised of two items. The first is, it appears there will always be owners and board members who resist the facts, numbers and so on. They will persist in their ways and the consequence will be money spent needlessly and in amounts higher than necessary. This will also result in higher fees for current owners, both today and in the future, which is when the tab will come due. The second part is about me. I really, really don't have to live here and my spouse and I have done so only because we choose to. I can move any time I wish which is an option not available to everyone here at BLMH. The work I have done for the past  years was a gift. My services will not necessarily continue to be available. Yesterday, when asked if I would continue on the board, I told those present during the association meeting that "I had received a better offer from a HOA in Hawaii." I am undecided. What would you do?

The Future
I look forward to visiting BLMH in 2034 to see the condition of the streets. I'll wager that the north section of Lakecliffe will be showing its age, but will continue to provide good service. Of course, most of those who argue against planning, preparation, programmed maintenance and cycles, or preventative maintenance and so on are also not planning in being here in 5 or 10 years. They most certainly won't be here in 20 years.

In 2034, there will be others living at BLMH and they will probably notice the condition of the streets. Some may notice the condition of the north section of Lakecliffe and compare it to the condition of other, newer portions of the streets of BLMH. They will wonder why it seems in better condition. You and I will know why that is so.

Tuesday, August 12, 2014

Lakecliffe - Asphalt Begins

2 comments

Bookmark and Share

The following were posted throughout the day. The earliest post was at 7:21am and is at the bottom. the most recent is at the top. 

Update 3:00pm - The street has been reopened
The "Road Closed" signs were taken down at 1:41pm. The August 8, 2014 notice posted by management stated "If the "Road Closed" signs are still up DO NOT DRIVE ON THE NEW SECTION OF LAKECLIFFE DRIVE until the signs are removed."  The "Road Closed" signs have been removed.

UPDATE 1:54pm
This photo and the message "BLMH Lakecliffe street is open" was sent to the HOA president at 1:54pm. At 1:55pm this response was received: "Hoo-rah!"



UPDATE 1:26pm
The final paving work is underway.

Surface Course Continues and Dodging Cars 12:53pm
The "ROAD CLOSED" signs and "Road Construction Ahead" signs are at each end of this section of the street. There is also the  "Street Closing set to occur Monday 8/4 - Tuesday 8/12" signs at each end of this section of the street, as well as hand carried and posted notices in each building entrance in the construction zone. Apparently, some of us are "special" and so this certainly doesn't apply to "me."




Surface Course as of 12:46pm

Surface Course at 12:01pm


Binder Course underway 10:40am

ORIGINAL POST 7:21am, August 12
I was at the street at 6:30am for an early meeting, but apparently the decision had been made to proceed. The paving company began arriving at 6:40am and by 7:00am the work was underway.






Monday, August 11, 2014

Lakecliffe - Update Monday August 11

0 comments

Bookmark and Share



UPDATE 5:30pm Monday, Aug. 11
The engineer retained for this project has been in communication with management, maintenance and the board. Here is the current status. 
The application of Prime Coat: Given the rain the project has taken on during the last 24 hrs., the use of the prime coat will not likely have the desired benefits.
The engineer recommends that if the site takes on any more rain between now and tomorrow morning, the prime coat should not be applied. Likewise if it stays dry from now until early tomorrow morning, the prime coat could be applied.
The construction services manager for the engineering firm will plan to be on-site early tomorrow morning to help make this determination. Management, maintenance and a representative for the board (me) will be there for the decision.
Bottom line:  We need to return the road to service.  

UPDATE 3:00pm Monday, Aug. 11 
If it doesn't rain tonight and if it is dry then work will resume tomorrow morning.  However, here is the latest NOAA.gov weather prediction at 2:52pm:

Tonight: A 50 percent chance of showers and thunderstorms. Patchy fog after 4am. Otherwise, mostly cloudy, with a low around 63. Light west northwest wind becoming northwest 5 to 10 mph in the evening.
Tuesday: A slight chance of showers before 1pm. Patchy fog before 7am. Otherwise, cloudy, then gradually becoming mostly sunny, with a high near 74. North northwest wind 10 to 15 mph, with gusts as high as 25 mph. Chance of precipitation is 20%.


UPDATE 9:08am Monday, Aug. 11 
It's official. Work will not resume today.

ORIGINAL POST 7:30am Monday, Aug. 11 
Thunderstorms entered the area at about 2:00am. Intermittent rain is to continue today and tonight.

No word at present as to when work will resume and the paving completed on north Lakecliffe.

Sunday, August 10, 2014

Lakecliffe - Update Sunday August 10

0 comments

Bookmark and Share
UPDATE 12:40pm, Sunday Aug. 10 
Over at Weatherunderground.com they say there is currently a 90% chance of a thunderstorm tonight. That could delay the paving. However, at present there has been no indication of a change in schedule and all residents in the construction area should plan on work beginning at 6:45am or possibly earlier. If rain does not arrive tonight, Monday morning could be a mad dash by the paving contractor to beat the rain.

Attempting to get certainty with the weather is very difficult. For example, here is the NOAA official weather forecast for Wheaton IL, last updated at 11:52am:

This Afternoon:   Mostly cloudy, with a high near 83. East northeast wind around 10 mph. Tonight: Mostly cloudy, with a low around 66. North northeast wind 5 to 10 mph.
Monday: Showers and thunderstorms likely, mainly after 1pm. Mostly cloudy, with a high near 82. North northwest wind around 5 mph. Chance of precipitation is 60%. New rainfall amounts between a tenth and quarter of an inch, except higher amounts possible in thunderstorms.
Monday Night: A chance of showers and thunderstorms. Mostly cloudy, with a low around 63. Northwest wind 5 to 10 mph, with gusts as high as 15 mph. Chance of precipitation is 30%.

UPDATE 3:30pm, Sunday Aug. 10 
This Afternoon: Partly sunny, with a high near 83. East northeast wind around 10 mph.
Tonight:  Isolated showers between 7pm and 4am, then scattered showers and thunderstorms after 4am. Mostly cloudy, with a low around 66. North northeast wind 5 to 10 mph. Chance of precipitation is 40%.
Monday: Scattered showers and thunderstorms. Mostly cloudy, with a high near 82. Light north wind increasing to 5 to 10 mph in the morning. Chance of precipitation is 50%.

Friday, August 8, 2014

Lakecliffe - Update August 8, 2014

0 comments

Bookmark and Share
UPDATE 4:00 PM, Friday Aug. 8. Notices have been posted in the foyer of each entrance in the construction zone. Residents should read the notices and comply. The street is closed for the weekend and cars will be towed.

Original Post 9:02AM:
Notices were posted yesterday, Thursday August 7 by management at the buildings in the construction zone. This provided the latest schedule information, information about trash pickup on Friday (today) and so on. Currently, the northern section of the street is closed until all construction is completed. Residents in the construction zone are being instructed that they can drive in only after the "ROAD CLOSED" signs and barricades have been removed.

The "Construction" signs were updated this morning. At 6:00am, HOA maintenance workers and myself were on hand to make sure trash and recycling vehicles had access. Trash and recycle bins were carried to the street and then put back on driveways for those addresses with dug-up drives.

At 7:00am, construction resumed.

At 8:30am the construction signs were updated with the latest information. The north section of the street will remain closed through the weekend. Paving is to occur on Monday.

Newsletters were distributed to the north half of the property yesterday evening.


Thursday, August 7, 2014

Construction Continues - The Votes are In

0 comments

Bookmark and Share
Click on the image to enlarge

Saturday, August 2, 2014

Lakecliffe - "Convergence"

5 comments

Bookmark and Share
con·ver·gence
kənˈvərjəns/

"The process or state of converging. To converge is to come together from different directions so as eventually to meet."

For this HOA the state of Lakecliffe Blvd was the result of the convergence of many dynamics within BLMH. Some can be traced to decisions made over decades. Some recent boards refused to make a decision and passed the problem to the current board.  The failure of Lakecliffe didn't "just happen."

But the reader might be inclined to take the position that with the completion of the replacement of this section of this street "It's over." Ah, yes, let's just "move on."

Is it really over? Some infrastructure issues are being slowly addressed and yes, an additional eight roofs are scheduled to be completed by fall. However, other streets are showing the same danger signs as did north Lakecliffe in 2008-9. While it is true that the current board has taken the steps for a serious engineering analysis of the streets in 2014 and a reserve study update to incorporate the findings of the study, it will be entirely up to future boards to deal with this and collect and spend the money. Future boards will have to decide what to do, when to do it and by whom. There is no guarantee for a good outcome.

In the recent past, some boards were incapable of doing this. Lakecliffe is a consequence.  There are other consequences, some remain unconcealed.

A question for future boards is this. Will the new streets be maintained, or not? With the completion of the roofing project will reserves be put aside each year earmarked for roofs and allowed to accumulate for 20 years? Or will the boards decide to pass the hat to future owners? It happened before and it can happen again.

Whatever future boards do, there will be consequences. So what converged to get us to this place in time? Here are a few factors to consider.

Conclusion - Provided here for those who want the executive summary
When things go wrong it's easy to look for simple answers. When an aircraft falls from the sky, the experts say that it is usually the consequence of mechanical failure and pilot or other human error. There is no one, single cause and human beings are usually involved as the decision makers that led to that aircraft failure.

So too with HOAs. When things go wrong some owners come to the then current board as the simple answer.

When serious infrastructure problems occur, it may be easy to point the finger at a construction company or builder, or a board, or a manager. I think its reasonable to say that these types of failures are the consequence of the complex interaction of people. People make decisions in a HOA, not one, but many and over a period of years. Those decisions determine fees and how and when they are spent. Those decisions require establishing priorities and allocating resources. Property managers and boards are not project managers, engineers or construction managers. Some management firms may include such individuals but that is not the skill set of the property manager. But memories are short, and when certain problems occur, then some owners will say "How did this happen?" Frequently it is the same people who promoted a certain course of action. Owners are an intrinsic part of the decision making process. Owners elect the boards and it is the owners who press to achieve certain results, including reducing fees.

In this post I've provided a scenario which presents Lakecliffe as a convergence of good intentions and some less than good decisions. Taken singly, each decision might seem reasonable and should not have resulted in failure. Each decision can be argued on it's own merits and has been, by numerous boards and a variety of board members. I suspect no one single decision made after construction resulted in the current condition of the street. Instead, a series of events, some of which began years before this street was installed all converged. Those events included finances commencing decades ago, the design and installation of the street, some long held beliefs about how to maintain a HOA, and beliefs about how to keep fees as low as possible. One factor was the conflicting demands and expectations of owners, and the attempts of various boards as elected representatives to satisfy the owners. Another is the capabilities of volunteer boards. Another is chronic staffing issues.

I am of the opinion all of the decision makers did so with good intentions. I suspect there was no overwhelming desire on the part of anyone for this street to fail. But fail it did. What do I mean by "fail?" I mean the early and premature expenditure of a lot of money to replace it. That's what I mean by "fail."

What were some of the contributing factors? Owners have pressed and complained about high fees for as long as I have been here; certainly since 2001. In 2008 the owners made it a point to put in place a board to correct that. Over decades a variety of boards made decisions to avoid spending money needlessly. The definition of "needlessly" varies from board member to board member. Each owner has a different definition of "essential" spending, but it is generally true that money spent for maintenance of "my" building, patio, walks, driveway, garage, lawn, etc. is money well spent. Design sometimes occurs in house, rather than by licensed professional engineers; there is a place for this, but the street should not one of them. Project management occurred in house. There is a place for this, but the street should not be one of them. Preventative maintenance did not occur, but spot patching and then larger patching did occur. Boards were slow to respond; this is inherent in the structure and makeup of volunteer boards, as well as the frequency of HOA meetings and a requirement that all such meetings be held openly. Replacement was delayed in an attempt to reduce expenditures and reduce owner fees. The street did not cooperate and failure accelerated. Boards were sidetracked by other issues, both social and substantive. In 2008-2012 Lakecliffe was not considered to be an emergency, and in 2008-2009 it was not even considered to be a problem worthy of discussion. In 2009-2010 it began as a nuisance. It was eventually elevated to the status of an inconvenience. By 2012 a realization of possible failure became a consensus, but catastrophic failure did not seem possible. We'd undergone a change in management and the board and most were baffled. After all, this street was supposed to be okay until 2021 or so.

The question to be asked is "What can a HOA do to avoid this type of situation?" Lakecliffe serves as a beacon. It provides an opportunity for change, and it can be used constructively to build a consensus that some change is really necessary. Not the political buzzword Change, but rather a shift in perspective, the way problems are approached, the way tasks are prioritized, the character and composition of boards, the delegation of duties to property managers, the proper use of professionals, and the role of owners. Most of the owners in this HOA have regularly paid their fees. Some boards had members who did the same, showed up at meetings and merely cast votes as their primary duty. Some change really is necessary. There is absolutely no consensus that it should occur and no one is empowered to make it happen.

There are many other infrastructure and organizational issues. They simply aren't as visible or obvious as Lakecliffe. Boards are comprised of micromanagers with a different emphasis or focus for each board member.  Programmed, cyclic replacement is frowned upon, with the painting program as the one unique and repetitive, guaranteed task at BLMH. Micromanagement supposedly reduces overall costs.  It also delays replacement, prevents certain maintenance such as streets and driveways and garages and even sealcoating and carpet replacement. I suspect it supports a "squeaky wheel gets the grease" approach. There has been a slow transition, but it is an uphill battle. Without a programmed approach, new boards are likely to drop out entire tasks, and they do.

It is my opinion that a variety of boards have accomplished quite a lot at BLMH since 2008. The pace has accelerated since then. However, it is also true that our infrastructure is aging and with that age there are additional problems becoming visible. Our reserve study does address the infrastructure issues, but cannot determine the lifespan of our water mains. However, there are some things that can be done to get a better grasp on that. The completion of the street analysis by a professional engineering firm will be important for updating the reserve study. The current status of driveways, garages and roof projects will also be incorporated. Future boards should have a much superior tool as a guide. However, it is up to the boards to decide to use that tool. Perhaps it is time to turn more of this over to professionals and fund a full time manager. Boards can be more involved in identifying problems, cost centers and fund sinkholes, figuring out supplemental sources of income, or social issues and keeping owners happy.

But a variety of owners are distrustful of the boards, managers and maintenance. Owners don't like the disruption caused by the infrastructure work. The pace has quickened and for several years it seems whole areas are a construction zone. This is a consequence of a promoted plan to delay such work for as long as possible, the acceleration of certain problems including aging roofs and dying trees, unforeseen events and Lakecliffe, and the game of  "catch-up."  There is a price to pay for delay and we today are paying it.

All owners really need to get a grip on financial reality.  Our fees are not going back to $175 per month, unless future boards find other sources of income and return to a day when adequate reserve accumulation was for future owners to accomplish.

Is real change necessary? Possibly not. This HOA got to this point and various boards dealt with all kinds of issues. How will we pay for this street replacement? Simply delay other work. So why should we change? Consider the age of this complex, consider the fact that infrastructure is failing,  be it streets or water mains or even the entrances, mail boxes and garage floors. Even the lakes pose a problem, but we are tied to Wheaton about that and our "tax and spend" neighbor COD. Nevertheless it does need to be addressed.

Consider the age of the board. Change is coming. It will be the decision of all of the owners if it is to be a transition or another series of costly disruptions. We all have decisions and choices to make. Make them well. If we do that and with a little luck and by the grace of God, our fees might actually improve and we might get better results.

Was it because of original design flaws?
BLMH has struggled for nearly 40 years dealing with and correcting design and construction flaws. These include roofs, patios, streets, garages, streams and ponds, and most recently owner fireplaces. Today the fireplaces have become the centerpiece and a primary concern for some owners. Some forget or prefer to be oblivious to the fact that the board owns units and we too have our personal fireplaces to deal with.

For some addresses the elevation of the buildings relative to the street is an issue. Some buildings were built so low that water could not flow properly to the streets. Any impediment, such as a thin layer of ice or snow, or even severe downpours caused a problem. This has required extreme diligence during any driveway or street repairs to assure that water flows from roofs to driveways to the street and then into the storm sewers. It has increased the cost of repairs, and the cost to maintain. Some driveways must be kept clear of all ice and snow. BLMH was built in such a manner as to be expensive to maintain. Some boards fail to observe this, and some have chose remedial action over correction because it appeared to be the lowest cost approach. Or perhaps the approach with offered the lowest immediate cost was chosen. However, it is not practical to solve some of these problems. The best situation possible is achieve the longest possible life at the lowest annual cost over the life of the structure, road, etc.

Was it because of construction defects?
Lakecliffe was reconstructed in [2002-3]. At the time, project management was accomplished in-house by property management. I have never seen the construction drawings and so I cannot state if the curbs and street were installed in accordance with the plans. An inability to produce drawings when asked has led me to question if they existed; the lowest cost approach would be a specification to replace in kind. It seems a properly qualified, insured and bonded engineering firm was not retained to prepare plans and specifications.

What we have recently determined is the thickness of some sections of asphalt were abnormally thin. The slope or pitch of the street and the crown was less than recommended guidelines. The street was rolled to the arrangement of the curbs and several areas of these could not provide the needed slope. A layer of "petromat" was installed between two courses of asphalt, the topmost of which was sometimes too thin. All of these factors combined to create a street which failed prematurely.

Knowing what happened has resulted in a more costly project. It was initially thought (by me in 2009 and as an owner) that we could simply strip asphalt and put in a new course.  As the disintegration of the street progressed, even with large patching of sections, it became apparent to me that simple asphalt replacement would be insufficient. BTW, in discussions with engineers, etc. I have NEVER revealed my personal opinions. Doing so could have influenced the result of any study, analysis and so on. What I have done is set a desired outcome; specifically "What do we need to do to achieve a street that is capable of normal lifespan with nothing more than normal maintenance?"

The current project is considerably more elaborate than simply peeling and replacing the asphalt, and will cost more than my $100,000 estimate performed as an owner in 2010, provided to that board and promptly flushed.

Was it because of insufficient funding?
It's useful to look at the street from the perspective of a board in place in 1998-2001. Consider the state of HOA finances at the time, the absence of a formal reserve study, and the complaints of owners about "too high fees." So what would most of us do as an elected, volunteer board comprised of ordinary owners in those circumstances? Would we spend thousand of additional dollars for surveying, plans, specifications and project management? Would we hire an independent testing lab?

This HOA has struggled for most of its existence with a variety of funding issues. Early fees began far too low for a 40 acre complex with numerous start-up defects and issues. Those fees did not include any provision for adequate reserves. Paying for the daily bills and some major breakdowns was the major issue. Is it a wonder that today some owners prefer a lack of financial planning and preparation? Is it any wonder that boards were elected and put into place because they refuse to do such planning? Paying the bills each month via the checkbook is the minimum standard. It worked before, didn't it?

Here's an example. The first bona-fide, unbiased reserve study was conducted in 2011, 37 years after construction of this HOA began. [After construction of BLMH there were] several periods of see-saw fees which created financial issues and stress for boards and owners. One prevailing attitude and accepted operating principle which emerged was "If we don't spend it we don't have to collect it."

There appears to be a belief that "Our fees are too high." This was most recently stated to me by a board member while we were observing the Lakecliffe reconstruction. I found that to be ironic. We're ripping out a street 12 years after installation and which I identified as failing only 6 years after installation and our fees are too high? I wonder what contributed to that opinion? Of course, no one ever comes up with a viable solution for permanent fee reduction. The prevalent approach has been to reduce fees now and let future owners deal with the consequences.

Some owners have preferred boards which will defer spending while attacking other boards in a crude attempt to have funds diverted their way. This provides the best of both worlds. "My fees are lower but I get the benefit of higher fees were such benefits provided to each and every owner." Their rallying cry became "What do I get for my money?" Some boards apparently supported this with a "squeaky wheel gets the grease" approach. In other words, only if there is a forceful complaint will certain problems be dealt with. That approach does create a problem as the word goes out. Eventually, owners get the word via the club or whatever and so the playing of the game expands among the owners. However, most of the money spent in such appeasement was nickle and dime. It's certainly easier to pour a section of walkway than to plan for and deliver the replacement of streets, roofs, 336 patios and decks,  84 garages, 84 entrances, 800 trees or water mains.

Boards contributed by avoiding certain expenses, such as failing to hiring engineers for certain projects, failing to assure  adequate supervision and failing to have a professional construction manager present for the street project. This would be expensive and of course, we got by without this in the past. But did we?

Was it because of a lack of reserves?
By 1999 the reserves were a shambles. In the first 37 years of existence, this HOA had never had a formal reserve study. In 1998-1999 a new management firm was brought in and boards were evidently made aware of the problem, as fees began to continuously rise each year as reserves grew. However, it didn't take long for owners to complain. This was a departure from the normal which was not communicated by the boards. The newsletters of that period don't give a hint of what is to come, or the long term financial goals of board and management. By 2001 owners were complaining "our fees were too high."

Was it because of a lack of planning or maintenance? 
In 1999 this HOA began ramping up fees. Apparently the new management had a different perspective about reserves. Streets were replaced several years later and reserves began accruing again for the next street replacement planned to occur several decades in the future. No program was put into place to maintain the streets, beyond patching any hole that might appear, a collapsed basin, etc. Six years after completion, in 2008 the street was identified by an owner as failing. This did not fit the financial plan. By 2010 street patching began and the street was identified by an owner as requiring $100,000 within 5 years. That however, did not fit the financial plan. In 2010-2011 board discussions about performing street maintenance, including crack filling were tabled. A manager argued it wasn't necessary and the board was disinterested. Besides, such maintenance wasn't in the budget. By 2011 an unbiased reserves study was made. It too indicated a street replacement in 2021 or so, based solely on the installed date of the street, not the current condition.

Finally, a board did authorize funds for an analysis of the street. It confirmed what was already known, but difficult to believe. The street was gone.

Was it because of resistance to programmed maintenance cycles?
At BLMH most, but not all maintenance is accomplished as needed. There is no regular preventative maintenance program for any of the asphalt surfaces in the HOA. That includes streets and driveways. At present new driveways are being seal coated within two years of replacement. Beyond that there is no plan in place for future seal coating or crack filling.

One area of difference in which there is a regular cycle is the painting of the buildings. Interior halls and the exteriors as well as structures (lampposts, gazebo, etc.) have wood replaced and are painted on a regular basis. This was every 5 years, but recently a board agreed to change this to a 6 year cycle so that the same number of entrances and exteriors are done each year. This change will smooth annual expenditures.

However, just about everything else at BLMH is not maintained as a cycle. Hallway carpeting is to be regularly replaced according to the reserve study, but it is not. It would be very easy to do this in tandem with the painting cycle, but one year later. Same for sealcoating of driveways and certainly for street preventative maintenance.

Is there a financial advantage to avoiding cycles? Apparently there is a belief that delaying maintenance "as long as possible" will reduce annual costs. This was the argument used for delaying roofs. There is another advantage. Some things will never happen because there is no directive given to perform that work. Ultimately, some repairs will grind to a halt. I can provide a list of such repairs for anyone who will listen and I do bring this to the attention of boards each year.

Is there a disadvantage to avoiding cycles and using a buffet approach? That's an approach where maintenance issues are laid out on the table and a board picks and chooses? One glaring problem is simply this. Unless a board issues a directive each and every year, then some things will never occur because they may never be placed on the table or if it is a list, some items may never come up to the top of the queue. In other words, certain repairs will simply be "dropped out" because there is no instruction to perform them. In combination with board turnover, this means that some things simply never happen because they are forgotten. Other, more pressing issues will displace many attempts to move some items to the top of the list.

There will always be breakdowns or owner upsets. These can overcome boards. In recent years there has been the COD expansion and creation of a dumping ground on our east property line, flooding in South Wheaton, disruption caused by new roofs with gutters and downspouts, other drainage issues, an IDNR dam permit, owners fireplaces, delinquencies, foreclosures, board turnover, etc.

Boards seem reluctant to do programmed maintenance. Would regular maintenance of the streets contribute to a longer life?

Was it because of staffing problems?
BLMH has been professionally managed for about 15 years. Prior to that time it had a single manager, but financial systems were manual, etc. For approximately 15 years it has also had professional maintenance. Boards are chronically understaffed and there is currently one board member for 56 owners. At various times some board members have had no assigned duties or responsibilities, other than to attend meetings and to vote.

Other issues have diverted boards. These include dealing with delinquencies, bad debt, owner fireplaces, a flood in south Wheaton, IDNR issues with the lakes, board issues with Wheaton's control of the lakes, 15 or more water main failures, owner complaints about COD, other projects, drainage problems, roofing, garages, patios, streams and pumps, common area patios, etc. Let's not forget owner personal issues, which at times occupied 1/3 of entire HOA meetings. Then there are the "simple" day to day operations.  Simply keeping this behemoth running and paying the bills are the areas in which a substantial amount of the HOA director and management resources go.

As BLMH approaches 40, infrastructure issues have taken center stage.  The roofing reconstruction project ran into a serious problem because of a failure to handle water flow created by the installation of new gutters which diverted flows and flooded some units. In 2008 a new board either wasn't aware of this or ignored it. For whatever reason drainage improvements didn't occur for several years, creating a backlog of problems and some unit disruptions. Of course, owners demand these problems be dealt with "immediately if not sooner."  One board in particular decided in 2008-2010 that what was really important was the replacement of management and the maintenance company. For good measure it was also decided to rewrite the rules.

BLMH has the same number of board members as a HOA with 20 units. In fact, some much smaller HOAs have fully staffed boards. BLMH does not. Yet, in recent years we have had a webmaster, a communications director and at least one board member with no assigned duties.

BLMH is a complex PUD. It is considerably more difficult to manage than a couple of town homes. The board is a working board, not some group of political figureheads. Some recent board members have thought otherwise, as have some owners.

We do have a professional management company, but we don't pay for a dedicated, full time manager. Nor have we done so for about 16 years. Doing so would result in higher fees, and we can't do that, can we? We have a few amateurs on the board to do these tasks. "Any money we don't spend is money we don't have to collect" as fees. Penny wise and pound foolish is the expression that comes to mind.

So six people like me spend hundreds and thousands of man hours keeping this place running. What a way to run a business! Is it surprising that this HOA has maintenance issues? Frankly, we're doing damned well considering the impediments.

Was it because of board turnover? 
Every new board has to come up to speed. Every new board member has to begin the arduous journey of comprehending just what is going on here. Most new board members are not prepared for the task at hand. Running a election campaign is easy. The problem in this HOA is that board members are working members. We're not simple figureheads who rubber stamp management's activities. We design and direct. Boards literally create the future. Our actions will determine the condition of this HOA 5 years hence, and the fees in 10-20 years. Could this have been a contributing factor to the failure of Lakceliffe? During the last HOA meeting, while discussing the costs of hiring a project manager to oversee the replacement of Lakecliffe, a board member objected and stated to the entire board and specifically to me "You could do this, couldn't you?"

With board turnover it's like the movie "Groundhog Day" and every year there is an election and then we may begin anew. Unlike the movie, the new board members don't have the benefit of prior knowledge. The election is a reset. It may provide the opportunity for mischief. As a board member I'm a fiduciary? What's a "fiduciary?"

A few years ago I prepared a document several pages in length to provide candidates and new board members an understanding of reality. Boards have been hesitant to use that document. I'll publish it here in a few days; perhaps it will serve another HOA. I don't do these things because I need a hobby. This is serious business and a lot of owner money is at stake.

Was it because the board is overwhelmed with minutia?
Discussion of owner fireplaces has been going on during just about every HOA meeting since the fall of 2011. Owners bring a POD on the property and put it in a driveway with no protection under the steel rails; they don't even notify management. Satellite antennas get in the way of building exterior maintenance or magically appear. Asked to correct that the owner response might be "You can't tell me what to do and I'll sue you." "The stream is not running"  "There are mosquitoes on the property" etc., etc., etc. Many owners demand hourly response and resolution.

Every project that becomes delayed joins a long list of "priority" tasks which increasingly absorb management and the board, as we strive to meet the needs of the 330, and to move this forward and retain perspective. Some owners could care less. Some apparently revel in creating disarray and diverting the board. for a very, very few the thinking seems to be "I paid my $300 and I will get my share." Some owners park habitually in "no parking" zones. Some owners bombard management and the board with phone calls or emails about their personal landscaping issues. Or mosquitoes or standing water or the street or a pothole or dust or COD or whatever.

From time to time some board members give up. Our HOA has had zombie board members; they are the walking dead. That is a problem because there really are some priority tasks, rules should be upheld and money needs to be spent to deal with issues, such as Lakecliffe. Progress needs to occur each and every month. If not, we fall behind and that creates additional problems and board stresses. Do we have unlimited maintenance resources and budgets? No we don't. So deferring maintenance piles on the hours and the costs. But the attitude seems to be "Some future board can deal with that." WRONG!

Apparently, for anyone driving south from Salisbury, Thames, Gloucester, Dover or Plymouth the replacement of north Lakecliffe really isn't a big deal, is it? After all, "only" 56 units have been directly impacted. That's less than 17% of the units in this HOA. Anyone living in the impacted area would feel differently. I live in that area. But as one owner who lives on Thames said last year with respect to a problem on north Lakecliffe, "It's no big deal." Yeah, right. And on Monday when cars are parked in every single available space on the propery, some of the residents will view this as an imposition and an inconvenience. The "social group" said "We're all neighbors." The replacement of Lakecliffe is another opportunity for the residents in this HOA to "walk the talk." However, for some residents and owners, that's something for only the board to do.

Looking beyond the problems of the 17% impacted by the street replacement, the board is also dealing with the issues for the other 83% of the owners. When each of us is the center of our little universe of problems, we each demand immediate action. Some boards have operated that way. "Give the grease to the squeaky wheel and ignore everyone else." I don't operate that way. Each owner is an equal.

Was it because of board failure to plan and prepare?
Boards are staffed by owners. Some owners never studied this HOA prior to running for the board. Some owners don't understand the duties and responsibilities of a board member. Some don't know what a fiduciary is.

Some have never read the governing documents. Or perhaps they did at the closing 10, 20 or 30 years ago. Or perhaps they relied upon their attorney.

On joining the board, there are two choices facing an ill-prepared board member. Simply float, show up at meetings and vote. or do absolutely nothing. One good approach is to repeat the statements of others during HOA meetings. "So let me understand this, you are saying that ........."

Some can't read a balance sheet. Some don't understand the reserves. Some don't understand this HOA is a PUD.  Some don't know what a PUD is. Some don't know what the difference is between operations, maintenance and capital spending. Some have difficulty with arithmetic.

Some choke when they see a bill from an attorney, engineer or whomever for greater than $100 per hour. Some go catatonic on seeing an invoice for $10,000.

Some have no available computer technology, or don't have easy access to email. Some have never built or used a spreadsheet. Some don't have a digital camera. Some don't have or use a cellphone. Some apparently can't balance a checkbook.

Owners, on achieving status as a board member will operate on the board as they do elsewhere in their lives. Some owners may struggle financially and they bring that with them. Some don't budget. Some have little or no savings. Some have no financial plan for next year. Some have no long term retirement plan. Some think that furnace will last "forever" and so should the streets, entrances, and so on. Some don't understand maintenance, or practice it at home. Preventative maintenance is a completely foreign concept. Some see rules enforcement as repression. For some, the most difficult thing they ever planned was that vacation on a cruise ship.

Was it because of the culture of BLMH?
Boards are created by the owners. A very few owners step forward to serve on the boards and some are elected to do so. The attitudes and beliefs of the owners determine the character and makeup of the boards. Every owner gets to vote. Only the motivated do so.

This HOA has some owners who have lived here for 20, 30 or more years. Many of them have never served on the board. Some remember the "good old days" when fees were much, much lower. Some owners got burned by purchasing at the height of the residential real estate market. Some discovered their newly purchased unit had a defective fireplace. Some hold that authority figure "the board" in utter contempt as the source of all things bad at BLMH. A few play a game called "Give me what I want and I'll go away for a few days."

It's taken an amazing amount of hard work by a small group of volunteers to get this HOA where it is today. Frankly, some boards obviously did an extraordinary job in the face of very difficult circumstances. I'm amazed by some aspects of this HOA, even today. From time to time I suspect board burnout has occurred. I say these things because I've studied this HOA in great detail.

Not all owners agree. Some have no idea of what it takes to run a HOA but they "know" that our fees are too high, they "know" that there is enough money, they "know" money is wasted, they "know" that the board is incompetent, some promote the idea that there must be fraud, and they "know" that a few handymen could keep this place going, and to paraphrase one owner "My cousin has a pickup truck and he would do a much better job of snow plowing at lower cost." They also "know" that any neighborhood realty firm could do a better job of professional management of this HOA.

Too many owners don't want to know the bad news, be it "foreclosures," "delinquencies," "budget issues," "rental percentages" or water main failures. Some want to avoid the bad news because they construe it to mean higher fees, which they dread. Others view this to be an apartment complex.

Some see rules enforcement including late fees as punishment or board repression. Some delinquent accounts have viewed the board as the enemy. Some view any board member who refuses to vote for lower fees as the enemy. A vocal few see BLMH as primarily a social organization and to this day a few think it should be a philanthropic organization in which they, of course, would be the beneficiaries. Others promote the HOA as "primarily a retirement community." Until recently many apparently didn't know or understand that this HOA is a Private Urban Development in which we own the water mains and the streets.

Some owners resent that their fees are spent elsewhere on the property. "It isn't fair that my fees be spent on that stream repair and bridge replacement on Thames."

Was it because of owner or board complacency?
Is it important for owners to vote and attend annual meetings? Should the owners study the candidates and then vote or is it better to sign the proxy ballots and say "Just fill in the votes for me, would you?" What's a minimum level for owner participation (casting their own votes) in the elections in a "healthy" HOA? Would you say it is 25%, or 33% or 40% or 50%? Would a higher percentage be better?

Some owners say "I paid my fees and I have done my fair share." Okay, and by that yardstick the only thing a board member need do is show up at about 8 meetings a year and vote. Don't read the management packet, don't prepare, don't do anything. Simply pay your fees and come to the meeting and do your duty. In fact, in recent years that is exactly what some board members apparently did.

Owners may view living at BLMH as owning an apartment which should appreciate in value. Some view fees as something optional, because as we all "know" the money is wasted. Therefore any dollar I give to the board is going to be wasted, isn't it? [The money doesn't go to the board or to management, but some owners hold it that way. It's easier to play games when one can direct their anger at the board and management.]

"It doesn't matter who I vote for." A significant number of owners just don't bother to vote during the annual elections. After all, we have a manager and things just get done; it's magic. The best candidate is one which promises to lower my fees; that's all that really matters.

Many owners seldom attend a HOA meeting and that includes the annual meeting.

Some owners have insisted that they don't read the newsletter. As for this blog, it would be used as toilet paper but for the fact it would cost money to print it.

Some owners don't have the slightest idea of what the board does, other than spending money and enforcing the rules. Apparently the board just approves the checks and collects fees. Some owners view the board as personal servants and the management as part of the concierge service. As one owner angrily complained to me "I'm a customer and I demand that you do [blah, blah, blah]. "

At BLMH with 336 owners, some apparently have the attitude "If I don't pay my fees this month, it's okay" after all, there are 335 others and we all know the HOA "has enough money."  Anyone who looks at the bank statement know that. After all, what will this HOA do with that $1 million dollars besides waste it?

Was it because board members may believe "If we don't spend it we don't have to collect it?"
That is really not a good way to run a business. But it sounds wonderful. Combined with a lack of preparation for HOA meetings, all that the board member need do is show up and create delay or vote "No."

This is so easy to do, this ploy is the "swiss army knife" for the obfuscating board member. Don't like a project? Ask for more study, or more research, or more plans. If that fails, just delay it a month and perhaps somebody will forget or recent events will overshadow it. When the task is again brought before the board, delay it again, and again and again.

There exists an even better ploy. Don't allocate any money for the current task before the board. That forces the manager, or the board member or whomever into a place where it's all a matter of their opinion. They can make those plans, sketches or whatever, and then we can ignore them next month, or throw up another barrier.

To deal with management, simply discredit the manager. Then no one is the expert. Voila' The problem solved! We can avoid spending any money outside the regular Operations & Management budget, which was previously approved.

Was it because of "Wild goose chases" and "Snipe hunts?" 
If all else fails, create diversions to keep board members busy. For example, "Norm, we think it would be best if you checked all of the clothes dryer vents on the property."

If that doesn't work the delaying tactic can then be employed. If these techniques are applied in tandem projects can be delayed and money saved, for years.

If all else fails, have a few owners come to the meeting and assail the board with their complaints. That is sure to derail the discussion and the spending.

If there is one thing most owners might agree on it is that Lakecliffe really needs to be fixed. That's not the way it was viewed a couple of years ago. Another benefit is it does give some of the chronic complainers something substantive and real to complain about. In this case, it has actually supported the board in taking positive action.

Was it because of the unrealistic expectations of owners?
Boards and owners sometimes think that things should happen immediately. Some owners see a big check balance at the HOA and they say "What do we get for our money?" In other words, in the event of an owner personal issue the money is there so the board should spend it. There are mosquitoes on the property, there is a broken slab of sidewalk, there is standing water over there, I want new grass, etc. etc. etc. These are trivial amounts. True, they do add up, but who tracks these? No one. Get it into the work order system and get the board to approve it and voila' it's a done deal. Management is empowered to spend a small amount and the savvy and the selfish know that. It's all about playing the game to one's personal advantage, and some owners do just that.

If management were not so empowered, it would be impossible to deal with a lot of the simpler maintenance tasks in fewer than 45 days. Why? Because every task would have to go before the board. With a board meeting approximately every 30-60 days, that would determine how rapidly a HOA could respond. More complex tasks do in fact, require a minimum of 45 days because there can be no board authorization to proceed. Emergencies, such as water main breaks are an exception.

For larger projects, the boards just don't say "Hey, Mr. Manager, get a specification and have that street replaced next month." Well, some might. We don't need drawings and specifications, or we can't afford them. So just hire a contractor. Now, that might be okay for some projects where the contractor has specialized knowledge and proven skill. So how can we tell the difference? When should we spend the money for additional expertise and when should we not? Is it prudent to go for bids? What's the complexity of the work? Why be concerned; if or when it goes wrong, a future board will have to deal with it. But we are a nation of gamblers, so we know we'll win.

Let's be real, shall we. There is no "all knowing and all seeing board." Each member is an elected volunteer and each is merely doing what every other owner should be doing if they were in that seat. The Illinois Condominium Act implies we are each fully qualified.

Was it because of a lack of courage and vision?
Making difficult decisions requires courage. The courage to take on a challenge and in the face of adversity to take the necessary steps.

HOA boards are comprised of fiduciaries. Fiduciaries act for all of us, not for some of us. Fiduciaries accept the challenge and take the steps to acquire the necessary education many of us won't or don't. Fiduciaries take on the challenge of dealing with a myriad of problems most of us won't or don't.

It takes courage to make difficult decisions. It takes courage to identify unpopular challenges and take them on. It takes courage to look ahead 20 years and operate for all owners, both present and future.

Some board members cannot do this. Some won't do this. Some see themselves as the consequences of a popularity contest and have the well being of the entourage as the desired goal. It is really difficult to make decisions that are unpopular for that group.

Each and every day, and with every decision, board members are required to have courage. Courage and vision.

Was the problem with Lakecliffe the consequence of a failure of courage and vision?

Was it because of board reluctance to spend money?
Boards are reluctant to spend money. Some actually freeze at the thought of spending $10,000. Others are aware that every single dollar in those bank accounts have been allocated. Therefor, shifting $100,000 as a consequence of anything other than a dire emergency is not something taken lightly; that sum represents $300 or more from the pockets of each dues paying owner. These decisions are darned difficult.

Each and every board member is concerned by the answer to the question "What will be the consequences of an unplanned major project?" However, running the numbers is sometimes a foreign concept for board members. Some will freeze with the thought "What if we make a mistake?"

So boards may prefer to delay until the last possible moment, or until the timetable and even beyond. Sounds like a valid strategy, doesn't it? Wait until just before that street collapses, or that roof leaks or that tree falls. Then get into action and spend the money. This will keep the reserves as high as possible for as long as possible and it will reduce fees? However, this so stresses management because there are a lot of other things to do including water main breaks, for example, or a foreclosure. Legal meetings and true breakdowns will take precedent. It will stress maintenance and the maintenance budget. We don't have an unlimited army of workers here, do we? It stresses boards because BLMH is like the Titanic and changing direction quickly is at best difficult and at times, impossible. Is it any wonder a HOA may skirt from from iceberg to iceberg?

Boards, being part-time volunteers aren't available 24/7 (Although some owners expect that). "What do we get for our money?"

When a consensus is finally, arduously reached to move forward, what really happens? Boards are required to discuss such money spending matters during open meetings. That means a unique major project can't be approved and accomplished in a week, or a month or even a year. . For example, the first roof replacement was in 2002. The second didn't occur for 6 years, but the board already had plans, specifications and a bidder list. Yet drainage improvements didn't occur and some units were flooded in 2008-2009. Such problems increase the costs for the HOA and a few board members understand this.

Was it because of an inability to distinguish between small problems and larger ones?
Knee jerk "call a plumber" action simply doesn't work on major capital projects. Those projects occur sequentially and each step is discussed during many HOA meetings. Each step may require one or more months simply to agree and approve each step. What is the true condition of the street, how serious is the damage and do we need an engineering analysis? Who is to perform that? What will it cost and should we spend that money? Who is to do the specifications and drawings (in house or not)? Should we hire an engineer? Should we get bids? Which engineering firms? What is the cost and is it worth it? Only after selection and award of engineering contract can the work on drawings and specifications begin. Once the first draft is received who will review them and when? After management and board discussion, back to the engineer. The engineer is requested to make changes. Then back to the board and management. Who is going to perform construction management? Go for bids and then approve which portions of that management. Select the paving contract and go for bids. Review bids and get engineering opinion. Board approval of bids. Coordinate actual construction dates with contractor's schedule and HOA schedules. Adjust schedules to avoid unnecessary delays and conflicts. Decide what to communicate to owners and when and by whom.

The patio and bridge at the Thames waterfall is an example. The board of 2008-9 discussed this problem but could not move on it. In 2010 the bridge, which required repairs to restore to safe condition was closed for several months. This got the attention of owners and dramatized the problem. It was finally worthy of serious board discussion. There were two immediate courses of action possible; temporary repairs or replacement. The board chose the band-aid, but it was finally possible to have a serious discussion during HOA meetings about moving forward with replacement. Even with that board agreement, it has taken four years to replace a walk, a bridge and repair a stream at Thames. The replacement patio has not yet been approved, but over a period of three years multiple sketches and concepts have been submitted and the area was marked by me because of board concerns about the dimensions of the patio. It could very well take another four years to complete this. Of course, delaying indefinitely means that money will never be spent. "If we don't spend it we don't have to collect it."

Many owners don't understand this and some really don't care. After all, "My personal problems should be the paramount problems in the HOA because I'm an owner and I paid my fees." (The other owners really don't know who is delinquent, and the board can't reveal this and I won't).

There was actually a serious effort underfoot to replace Lakecliffe in 2013 with a board consensus that it really, really needed to be done. But the HOA was unable to get all the necessary pieces into place for that to occur during 2013. (Hire the engineer, get approved specifications, approved drawings, go for bids, contract award, determine who is to do project management, etc.).  There were discussions about how late in the year to possibly do repave. Of course, putting in roads is dictated by the operation of the asphalt plants. If the board screws up, well, as that one owner said about his/her current inconvenience "The board should pay for this." Instead the street was patched yet again.

It seems we have sufficient funds when it comes to owner inconvenience, but not enough to move forward on projects. That's the double standard with some owners. Any HOA board that operates in accordance with the whims and wishes of these people will fail, as will the HOA.

Boards are merely owners wearing a different hat. North Lakecliffe was identified as failing in 2008. Boards for a variety of reasons were slow to respond. Being told in January 2010 that we will have to spend $100,000 on this was not something a board wanted to hear.

By the time there was a board in place and a consensus on that board that Lakecliffe was failing and action was required, it was already too late. Then it became merely another item on a list of items requiring "immediate action."

Was the attempt to run this HOA as a social club a cause?
Social clubs might view collecting fees as a secondary objective. In fact, in some clubs "If you can't pay your fees, that's okay." Social clubs are based upon acquiring members and providing activities. For example, garage sales, picnics and outings. And finding people willing to do the work to organize and publish these activities in a club newsletter.  If an attempt were made to run a HOA as a social club and if paying homeowner fees became "optional" what would be the consequence? If the emphasis of a board was on social activities instead of running the business, would that delay unscheduled capital projects? If such a board also took the perspective "If we don't spend it we don't have to collect it" as part of an approach to reduce fees, would that delay unscheduled capital projects?

Would such an approach result in a reluctance to enforce the rules, and would that increase the delinquencies?

If a board allows budget shortfalls to accrue and increase as a consequence of a failure to collect fees, will that impact capital projects?

Was it because of the attitude about HOA fees and finances?
Some owners don't want to know about any financial problem that may result in higher fees.  Other owners don't understand the nature of infrastructure failures or the costs of dealing with them. "Just get a handyman and lower my fees."

"I'm paying $189 per month in fees and that certainly should never increase. After all, we have enough money. I know this because "so and so" told me." "The board really needs to get spending under control; my fees should not be going up and up and up!" [Quotes from 2001]

"If BLMH was well run, there would be no need for fees to go up, ever!"

"I'm selling my unit. I expect to be reimbursed for my share of the funds in the HOA bank account."

"We have enough money", "We have more than enough money", "We really have too much money!"

"I love the 800 trees, but the board spends too much on tree maintenance each year." I really love that comment by an owner. Yes, but that maintenance money includes the removal of dead and dying trees, which now requires $thousands per year. [In 2009 I asked a board member about our tree reserves; I was concerned about the rising cost of dealing with dead, dying and diseased trees. I was told "trees last a long time." At the time we had no reserves for this, apparently didn't need them and never would.]

Was it because of board failure to communicate?
Owners weren't informed of the potential problem with Lakecliffe in 2010. Nor were they advised of the financial implications. Why is that? As a consequence, any new board member was completely unawares of the seriousness of this problem.

Communication by boards is one of those really difficult chores. Some boards see it as optional and to be done after everything else. Besides, there really isn't anything new going on, is there? But we do get new owners each year, so how are they to know what's going on? For a new owner it's a brave new world. Some board members see communications as a waste of time. Some are concerned about saying or writing anything that could be held to be a "promise." Some are simply unwilling to make a commitment to the owners.

Some boards avoid bad news or may have difficulty determining what is really going on in a HOA. What is the direction, what are the initiatives, what are the problems that determine the finances, and so on. Every new board is a reset in HOA direction. Every new board needs time to "get up to speed." So what to write about? If all else fails we can write about architecture in England, or have a page on the resident of the month, or whatever.

To add to the issue, some owners don't want to be treated as shareholders. However, it's my opinion that it is the duty and responsibility of the board to publish communications that reflect that. Boards are required to publish budgets and annual financial reports. After doing so, boards can do whatever they like about communications.

It can be really difficult to assemble communications because one has to understand what's really going on. "Every owner gets the annual financial statement and a budget. So why read it to them?" Here's a thought. Why not tell them why we are saving and what we intend to do with that money and when? Tell owners how well or how poorly we are doing to meet these budget goals?  "That won't work because some people will say we made a promise and we can't do that."

Okay, so in the absence of communication we'll let owners simply make up anything they want about what the board is doing. "They will do that anyway." Sure, and some will read between the lines or misconstrue what is written. But many won't. While the 80% may be complacent, they aren't the 20%. "People don't read the newsletter." That's not my problem.

A real question is and remains "What is to be communicated?"  Another is, "What's really important?"

Boards cannot divulge certain aspects of HOA operations. Who is delinquent, for example. Or who is foreclosing, or who is breaking the rules. But we can provide statistics, can't we?

Is BLMH too large to succeed?
This remains unanswered. Boards remain understaffed.

But let's look at the flip side.  In recent years any owner who may have avoided paying their fees for months obviously decided this HOA was "too big to fail." Any board unable to reign in delinquencies must have decided likewise. However, such financial problems create other pressures and distress.  With owner financial distress, "bad debt" and delinquencies, how should a board respond? Delaying capital expenditures is one way. Delay spending money. Avoid street preventative maintenance. Did this contribute to the condition of Lakecliffe?

Conclusion
When things go wrong it's easy to look for simple answers. When an aircraft falls from the sky, the experts say that it is usually the consequence of mechanical failure and pilot or other human error. There is no one, single cause and human beings are usually involved as the decision makers that led to that aircraft failure.

So too with HOAs. When things go wrong some owners come to the then current board as the simple answer.

When serious infrastructure problems occur, it may be easy to point the finger at a construction company or builder, or a board, or a manager. I think its reasonable to say that these types of failures are the consequence of the complex interaction of people. People make decisions in a HOA, not one, but many and over a period of years. Those decisions determine fees and how and when they are spent. Those decisions require establishing priorities and allocating resources. Property managers and boards are not project managers, engineers or construction managers. Some management firms may include such individuals but that is not the skill set of the property manager. But memories are short, and when certain problems occur, then some owners will say "How did this happen?" Frequently it is the same people who promoted a certain course of action. Owners are an intrinsic part of the decision making process. Owners elect the boards and it is the owners who press to achieve certain results, including reducing fees.

In this post I've provided a scenario which presents Lakecliffe as a convergence of good intentions and some less than good decisions. Taken singly, each decision might seem reasonable and should not have resulted in failure. Each decision can be argued on it's own merits and has been, by numerous boards and a variety of board members. I suspect no one single decision made after construction resulted in the current condition of the street. Instead, a series of events, some of which began years before this street was installed all converged. Those events included finances commencing decades ago, the design and installation of the street, some long held beliefs about how to maintain a HOA, and beliefs about how to keep fees as low as possible. One factor was the conflicting demands and expectations of owners, and the attempts of various boards as elected representatives to satisfy the owners. Another is the capabilities of volunteer boards. Another is chronic staffing issues.

I am of the opinion all of the decision makers did so with good intentions. I suspect there was no overwhelming desire on the part of anyone for this street to fail. But fail it did. What do I mean by "fail?" I mean the early and premature expenditure of a lot of money to replace it. That's what I mean by "fail."

What were some of the contributing factors? Owners have pressed and complained about high fees for as long as I have been here; certainly since 2001. In 2008 the owners made it a point to put in place a board to correct that. Over decades a variety of boards made decisions to avoid spending money needlessly. The definition of "needlessly" varies from board member to board member. Each owner has a different definition of "essential" spending, but it is generally true that money spent for maintenance of "my" building, patio, walks, driveway, garage, lawn, etc. is money well spent. Design sometimes occurs in house, rather than by licensed professional engineers; there is a place for this, but the street should not one of them. Project management occurred in house. There is a place for this, but the street should not be one of them. Preventative maintenance did not occur, but spot patching and then larger patching did occur. Boards were slow to respond; this is inherent in the structure and makeup of volunteer boards, as well as the frequency of HOA meetings and a requirement that all such meetings be held openly. Replacement was delayed in an attempt to reduce expenditures and reduce owner fees. The street did not cooperate and failure accelerated. Boards were sidetracked by other issues, both social and substantive. In 2008-2012 Lakecliffe was not considered to be an emergency, and in 2008-2009 it was not even considered to be a problem worthy of discussion. In 2009-2010 it began as a nuisance. It was eventually elevated to the status of an inconvenience. By 2012 a realization of possible failure became a consensus, but catastrophic failure did not seem possible. We'd undergone a change in management and the board and most were baffled. After all, this street was supposed to be okay until 2021 or so.

The question to be asked is "What can a HOA do to avoid this type of situation?" Lakecliffe serves as a beacon. It provides an opportunity for change, and it can be used constructively to build a consensus that some change is really necessary. Not the political buzzword Change, but rather a shift in perspective, the way problems are approached, the way tasks are prioritized, the character and composition of boards, the delegation of duties to property managers, the proper use of professionals, and the role of owners. Most of the owners in this HOA have regularly paid their fees. Some boards had members who did the same, showed up at meetings and merely cast votes as their primary duty. Some change really is necessary. There is absolutely no consensus that it should occur and no one is empowered to make it happen.

There are many other infrastructure and organizational issues. They simply aren't as visible or obvious as Lakecliffe. Boards are comprised of micromanagers with a different emphasis or focus for each board member.  Programmed, cyclic replacement is frowned upon, with the painting program as the one unique and repetitive, guaranteed task at BLMH. Micromanagement supposedly reduces overall costs.  It also delays replacement, prevents certain maintenance such as streets and driveways and garages and even sealcoating and carpet replacement. I suspect it supports a "squeaky wheel gets the grease" approach. There has been a slow transition, but it is an uphill battle. Without a programmed approach, new boards are likely to drop out entire tasks, and they do.

It is my opinion that a variety of boards have accomplished quite a lot at BLMH since 2008. The pace has accelerated since then. However, it is also true that our infrastructure is aging and with that age there are additional problems becoming visible. Our reserve study does address the infrastructure issues, but cannot determine the lifespan of our water mains. However, there are some things that can be done to get a better grasp on that. The completion of the street analysis by a professional engineering firm will be important for updating the reserve study. The current status of driveways, garages and roof projects will also be incorporated. Future boards should have a much superior tool as a guide. However, it is up to the boards to decide to use that tool. Perhaps it is time to turn more of this over to professionals and fund a full time manager. Boards can be more involved in identifying problems, cost centers and fund sinkholes, figuring out supplemental sources of income, or social issues and keeping owners happy.

But a variety of owners are distrustful of the boards, managers and maintenance. Owners don't like the disruption caused by the infrastructure work. The pace has quickened and for several years it seems whole areas are a construction zone. This is a consequence of a promoted plan to delay such work for as long as possible, the acceleration of certain problems including aging roofs and dying trees, unforeseen events and Lakecliffe, and the game of  "catch-up."  There is a price to pay for delay and we today are paying it.

All owners really need to get a grip on financial reality.  Our fees are not going back to $175 per month, unless future boards find other sources of income and return to a day when adequate reserve accumulation was for future owners to accomplish.

Is real change necessary? Possibly not. This HOA got to this point and various boards dealt with all kinds of issues. How will we pay for this street replacement? Simply delay other work. So why should we change? Consider the age of this complex, consider the fact that infrastructure is failing,  be it streets or water mains or even the entrances, mail boxes and garage floors. Even the lakes pose a problem, but we are tied to Wheaton about that and our "tax and spend" neighbor COD. Nevertheless it does need to be addressed.

Consider the age of the board. Change is coming. It will be the decision of all of the owners if it is to be a transition or another series of costly disruptions. We all have decisions and choices to make. Make them well. If we do that and with a little luck and by the grace of God, our fees might actually improve and we might get better results.