My Basic scenario for Roof and Driveway Replacement 2008 The chart indicates funding accumulation versus savings for expenditures This is explained in the post. |
Note: click on images to enlarge. This post looks at what is required to create a reserve study. It looks at some of the scenarios I created to determine how to responsibly complete a large maintenance backlog at the association. It also includes a snapshot of the financial situation facing the association in 2010. I post this so current boards can avoid some of the problems and mistakes that occurred in the past. I also post it to provide current owners with some insights. One of the most tired questions I was asked during my 8-year tenure on the board was: "How could this happen?" Well, one reason is because "Ignorance is bliss." There are methods to unconceal reality, but boards and owners must choose to use them.
In this post, because it includes a variety of scenarios, you will see a variety of numbers. In fact, as condition reports, surveys and actual repairs are made, we get better projections because we have real costs and real condition reports, rather than estimates to use. Board can choose to avoid Reserve Studies, or to use Reserve Studies as "worst case" scenarios or as "best case" scenarios. They can choose to avoid getting periodic, formal updates, too. However, without accurate condition surveys and reports, any reserve study is at best a "guesstimate" and must be considered with a dose of skepticism. Personal agendas may interfere and I have known board members who always argued for the worst case scenario and the higher commensurate fees.
In fact, when good studies are made, with extensive and accurate condition surveys and reports, and maintenance backlogs are eliminated, the specter of huge unknowns diminishes. Certainty improves, but should be approached with humility.
Thanks to the boards prior to 2009, the association did, indeed face a "worst case" situation in 2009. I never considered my time on the board as creating anything. My time was absorbed in remediation work, cleaning up the problems and messes created by others, particularly those earlier boards.
Reserve studies and Replacement Fund numbers are useful, up to a point. Boards must balance annual and reoccurring condition surveys, possible expenditures, funding plans and the finances of the owners. That's what fiduciaries are supposed to do. (Note 3).
It seems do boards have difficulty making good decisions. For example, in the fall of 2009 the board discussed the situation about the driveways in the association. I'm going to quote my blog post of October 7, 2009:
".....there have been discussions during quite a few meetings regarding the state of driveways. Here is a summary, but not necessarily in the order of the actual events. The discussions included aspects of the how and why of performing these repairs. Unit owners attending the meetings brought some of the problems they were having to the attention of the board. They stated issues they faced last winter. There were a number of discussions over several meetings about ice, heaving driveways, heaving garage floors, standing water, water entering garages, methods and options for controlling run off and the flow of water from roofs, etc. The state of driveways and water was described as a "serious" problem by several members of the board. The board authorized the management company to complete a thorough survey of all driveways and rate them. At a subsequent meeting the manager reported on the driveways most in need and those had been ranked. Discussion at various meetings was interrupted by events I have reported in earlier posts. Eventually discussion at meetings resumed. Details of asphalt installation and concerns were stated regarding the unique nature of many of the driveways and even the uneven traffic patterns. Concern over weather interference, specifically the closing of asphalts plants in the fall and the need for urgency was pointed out. Finally, at a meeting the board discussed the results of inspections by our Architectural Director and our Landscaping Director.
The Architectural Director made a presentation and stated there were sufficient funds to do some, but not all of the driveways. He requested that seven (7) driveways be approved for repair and replacement in 2009. He made further statements regarding the criteria for selection.
The board voted and the motion was passed. There was a single NO vote cast. That vote was cast by our Communications Director."
The board that voted replaced most of an earlier, long running board in September 2008.
The Reserve Study indicated that the costs to accomplish the above would require $3,046,000. All work was to be completed by 2016.
Furthermore, there were serious problems with the condition of deteriorating streets. In 2011 the board was advised by an engineering firm hired to provide replacement fund guidance. "We recommend that the Association plan for a phased total replacement of the asphalt streets and parking areas....concluding by 2022."
As recommended, and based upon condition surveys and inspections the Boards 2014-2018 made major repairs and replacements to streets n a systematic, logical manner. The boards 2019-2021 decided not to continue this program.
In fact, there were flaws in the 2010 study. For example, I determined that the square footage of driveways and adjacent asphalt excluding streets was understated. I've included a small portion of my spreadsheet in this post and the post in the next link explains how I determined this and provides some budget numbers.
Click on: Budgeting - Driveways and other Projects October 2010
Furthermore, the cost per square foot to replace was also understated. Bids obtained by the board in 2010 were 91.7% higher or nearly double that anticipated.
Using the estimated replacement cost for roofs and adding the 2010 price to replace driveways resulted in a much higher estimated cost and Replacement Fund expenditures anticipated for 2010-2015.
- Revised total cost to replace roofs and driveways: $3,651,000 to $3,752,000
- Cost to replace the remaining driveways not replaced in 2010: $783,873.
- Total amount in reserves as of December 31, 2010: about $1,400,000.
- Budgeted contribution to reserves for 2010: $330,000.
- Replacement Fund balance would be a large shortfall as of December 31, 2015 with many streets remaining to do: -$687,000. To raise this amount of money, an additional $137,400 each year for five years would have to be levied on owners.
- At the end of 2015, the amount in the replacement fund (reserves) would be zero, even if the annual budget allocation was increased via fee increases.
- Expenditure to replace identified items by 2018, excluding additional for streets: $4,337,000
- Expenditures including all streets, the period 2012-2022: $5,737,000
- Much higher annual allocations to reserves was necessary.
- One possibility is to do what was necessary to come up with a viable plan, but also do everything possible to minimize further fee increases. Now that's what we call an oxymoron.
- Another possibility is to resign from the board and leave this for others to deal with.
- I chose to do the work and come up with a viable plan. That plan would require a lot of work on the O&M budget to identify areas where expenditures could be reduced while maintaining or expanding services. It would also require some serious planning about how to catch up with the maintenance backlog in a responsible manner.
- What the current situation was,
- Board decisions to be made,
- What the board was doing,
- What the future looked like,
- This was a solvable problem,
- It would be difficult,
- There was a light at the end of this tunnel, and,
- There was at least one on the board who would lead the way and get the job done.
- Video example of one of my annual meeting presentations: Click for President's 2016 Address
In an earlier post "The Replacement Fund and Owner Fees" I delve into the fees, the condition of the Replacement Fund and some aspects of the maintenance backlog. (Note 1). In this post I provide a snapshot of what was determined in a reserve study.
The Replacement fund has this definition:
- Replacement Fund [Reserves]. "This fund is used to accumulate financial resources designated for future major repairs and replacements of the elements the Association has a duty to maintain."
Owner fees are the source of the money for the Replacement Fund and the Operating & Maintenance budgets. Boards are tasked with determining and levying the fees on owners for both the Replacement Fund and the Operations and Maintenance (O&M) budget. The Illinois Condominium Act (ILCA) empowers a board of fiduciaries to to so. (Note 2, 3).
A Reserve Study is useful, but it is only a suggested plan, and these plans can frequently change. A reserve study may be incomplete and boards need to do a lot of additional research in order to be fully and properly informed. Property conditions change annually and frequent surveys, inspections and reports must be made. Deteriorating infrastructure such as Dover and Plymouth must be closely monitored.
Boards should use the Reserve Study as one of multiple tools and sources at their disposal when making decisions. Rigidly following a Reserve Study schedule does a disservice to owners because:
- The plan is an estimate of useful life of the elements on the property,
- The Reserve study is only as good as the information used to create the plan.
- All plans are fallible and contain inconsistencies and errors,
- There are other things to be considered, including the owners.
- Ultimately, no matter the circumstances the property must be maintained. Painting the buildings is not sufficient.
Prior to making an offer to purchase a unit in 2001 I reviewed certain Association financial documents. I gave these to my accountant and asked his opinion. We independently concluded that the Replacement Fund was insufficient. G and I also interviewed owners we met while walking the property. They had issues with recent fee increases. I decided to create a series of spreadsheets to monitor the finances of the association. Using those spreadsheets I created charts as visual aids. I continued to do so while on the board and thereafter.
During my board tenure, I ran a variety of scenarios and discussed with the board. That's one of the methods used to control fee increases. Operations and Maintenance (O&M) Budgets and reserve expenditures were controlled using actual condition surveys, etc.
One method was implementing cost controls on the O&M budget. Cost centers where improvements could be made were identified and plans implemented to maintain or improve services while controlling costs. Doing so will manage fees extracted from owners, and may create budget surpluses.
As an example, the painting cycle was increased from five years to six years, reducing the annual painting budget. Furthermore, instead of painting from 8 to 12 or more buildings each year, the number painted was the same each year. The association has 40 large and four small buildings, the small are the equivalent of two large. If we treat the two of the small buildings as a single large building, then seven such building would be painted each year in 6-year cycle. The painter wasn't pleased with this and neither was a long serving board member: "We never did it that way". The board voted for this change, but by 2018 the proposals were reverting to the old method. Another reason I left the board. "You can't teach an old dog new tricks" is an expression and it applies to some people, too.
- A determination of the useful life of each of the elements on the property. Engineers, architects and specialized contractors have this knowledge. Elements include roofs, driveways, garage floors, streams, streets, lamp posts, water mains, etc. However, the materials, and methods of construction as well as the use of the elements are to be considered. These factors when combined determine the useful life. Useful life is sometimes estimated as a range of years. For example, a roof made of basic 3-tab asphalt shingles may have a useful life of 15-20 years, depending upon the environment, underlayment, etc. Higher end and more costly architectural shingles and roofing systems may have a useful life of 24-30 years.
- The age of the various elements on the property must be known. This includes roofs, driveways, garage floors, streams, streets, lamp posts, water mains, etc.
- A site review and condition analysis is made to determines the actual condition of each of the elements.
- Using Items 1, 2 and 3 above, an estimate is made of the remaining useful life of the various elements on the property. The elements includes roofs, driveways, garage floors, streams, streets, curbs, walks, entries, lamp posts, water mains, etc.
- An estimate is required of the annual cost to maintain each element, and an estimate of the cost to replace at end of life. This includes roofing replacement, driveway asphalt replacement, curb repairs and replacement, etc. It is prudent for boards to consider annual cost to maintain when determining the actual time to replace. There is a point at which risks of failure and annual maintenance costs are excessive. Someone has to monitor and make that determination.
- A calendar is constructed, year by year which determines a schedule for the replacement of each element over a period of years. A long term calendar has a span of 30 or 40 years.
- The repair and replacement plan is accomplished in groups of elements according to the schedule. The initial schedule and grouping is called a phase. For example, the initial cycle of driveway replacement may be a plan to replace 1/8 of the driveways in a single year, let's say in 2009, and to repeat for for 8 consecutive years until all driveways are replaced in. Therefore all driveways will have been replaced in a single 8-year period. Subsequent cycles may be different. For example, with all driveways replaced and in "good" to "excellent" condition, they will be allowed to age for 15 years with minor repairs and sealcoating, until the next cycle begins in the 16th year after the previous replacement. That next cycle may use a future plan to replace 1/10th of the driveways each year.
- Using the schedule above, an Expenditure plan is determined. This indicates the monies that will be spent to replace each element at end of useful life. The expenditure plan will indicate the annual amount for each element of each year of the calendar. Summing those annual amounts will give a total expenditure necessary each year, according to the plan.
- A Funding Plan is created to determine the costs each year required to pay for the Expenditure Plan. The funding plan will include an amount required each year of the calendar.
- A Fee Schedule is created to allocate sufficient fees to the Funding Plan.
- Scenarios are constructed to include end of life deadlines, determine annual expenditures and the fees to be extracted each year from owners. The scenarios provide a range of possible solutions and of course, boards must select solutions that keep fees reasonable. The board then selects a scenario comprised of all of the elements that meets the criteria.
- The entire Expenditure Plan is added to projected (estimated) Operations and Maintenance (O&M) budgets. Doing so determines the total fees required from owners.
- With all of the above information above, boards then revise the scenarios and plans to accommodate the financial ability of owners while maintaining the entire property. The calendar or schedule of the Reserve Study is a guide for the board. Boards must establish priorities. A failure to do so will result in a defective implementation of the plan. For example, various reserve studies have included complete replacement of all of the exterior panels on the buildings, entire replacement of entries, etc. Boards 2010-2018 continued maintenance efforts on those elements as an alternative to replacement. If a board chooses otherwise, an additional
- should be reviewed annually and updated frequently based upon the current realities.
- Cost to replace roofs and driveways: $3,651,000 to $3,752,000.
- Amount in the replacement fund: Insufficient.
So, how much did the association actually spend to do seven driveways? We spent 53.57% of the paving reserves on 14.59% of the driveways, as based on area of all driveways and the area of the driveways replaced in the 2010 contract.
Portion of my Driveway Survey spreadsheet, October 2010 |
- Replacement cost, at 2010 prices = $6.71 per square foot.
- Cost per ton, CA6 Road rock (underlayment).
- Cost per ton, removal of unsuitable materials.
- Cost per unit, asphalt, installed.
Driveway replacement Schedule 2009-2010, my spreadsheet |
Roofing Replacement Schedule per Newsletters 2009-2010, my spreadsheet. This does not include 1775-1777 Gloucester, replaced 2003-2004. |
Examples of Damaged Roofs and Missing Shingles 2008-2009 "Visible to the naked eye" |
- Two roofing costs. I used $40,000 and $45,000 each. This did not include attic insulation nor did it include drainage improvements required by the relocation of downspouts to the building entries. Visit 1775-1777 Gloucester for the drainage improvement made for that first roof, completed 2003-2004. In 2011 the association was experiencing flooding at entries and I had a backlog of such improvements to do because the boards of 2006-2010 didn't include that work.
- Driveway average costs of $6,000 each. In fact, there are a range of sizes at BLMH. I made later, more sophisticated analysis using aerial views and actual measurements.
- In 2007 the board had allocated $263,915 in fees to the entire Replacement Fund. This included all elements of the association such as driveways, streets. roofs, streams, concrete, lighting, carpets, etc.
- I used an annual allocation addition of $330,000 via fees. That was unrealistic, but seemed to be where the boards of 2001-2008 was going.
- The amount in the Replacement Fund in fall 2008 was about $1,000,000 according to information revealed by the board and official documents.
- This was a "best case" scenario looking at the condition of the Replacement Fund. The approach used the entire Replacement Fund to replace the roofs and repair or replace driveways. To accomplish this in a reasonable time little or no reserve funds would be available for other elements prior to December 31, 2013. This was an unrealistic approach, but this seemed to be the direction of the boards prior to 2008.
- The analysis and charts indicated that sufficient funds might be collected and accumulated by year end 2013, if no other elements were replaced or repaired. However, that was a "best case" scenario. Thereafter, a surplus might be created and available for repairs and replacement of other replacement fund elements. Of course, the magnitude of the backlog could absorb all fees collected for the Replacement Fund for a number of additional years. (I flagged Lakecliffe street as a serious problem and it was failing).
- From January 1, 2013 to December 31, 2020 these scenarios could increase the Replacement Fund balance. If all roofs and driveway repairs were completed by December 31, 2013 the Replacement Fund balance would be nearly $0 as of 12/31/2013.
- Replacement Fund surpluses would accrue commencing January 1, 2014, but might be spent on other maintenance issues as soon as collected. If unspent, these scenarios could grow the Replacement Fund to $2,378,337 or $2,588,000 as of December 31, 2020. However, other repairs and replacements throughout the property would require all of these funds, and more. In other words, all Replacement Funds collected would be spent on streets, water mains, lighting, carpeting, decks, concrete patios and walks, etc.
- It would take further analysis to determine the costs to replace Lakecliffe, garage floors, repair streams, ponds and 30 year old pump pits, replace common area decks and bridges, large outdoor lighting poles, the gazebo, concrete patios, unit decks, and accommodate garage floor replacements, etc. My list and surveys was extensive. Which is why I categorized my charts for roofs and driveways as "best case scenario". I estimated 8-10 years to catch up with the backlog and address other elements nearing end of life.
A Range of Scenarios were created using Reserve Studies 2010 to 2015
You will notice a tab in the spreadsheet "Water Sewer" because I was delving deeper into costs at BLMH and was actively working on transferring the mains to the City of Wheaton |
Incomplete south entry signage replacement to be completed in 2022. The board of 2021 decided to make this a priority. |
- Projected Reserve shortfall over the next 5 years: more than $1,130,000
- Projected Reserve Balance December 31, 2015: $0 (all reserves spent by 2016)
- Reserve Funds required within 5 years, excluding streams, water mains, trees, garage floors: $4,185,000.
- Total of the Replacement Fund available (Reserves): $1,550,000.
- Possible additional reserve collections within 5 years: $1,500,000.
- Roofs requiring replacement: 43
- Roofing Project costs, excluding drainage: $2,850,000.
- Condition: Fair. Weathering and deterioration of the exposed shingles has progressed to the extent that the roof system (43 of 44 roofs) is approaching the end of its useful life.
- Useful Life: 15 to 20 years when new.
- Remaining Life of roofs on the property: a range of from - 3 years (condition of some roofs 3 years beyond useful, immediate replacement required) to others with 7 years remaining (maximum life).
Roofing Program - My Partial Spreadsheet 2010 Not shown: Reserves accumulated 2010-2041 and annual expenditures, Those amounts are in another row of cells. |
Roofing Program - My Expenditures Spreadsheet |
2010 - Driveway plan. With a large backlog of driveways in "poor" and "fair" condition a plan was necessary. (c) N. Retzke 2010-2021 |
2010 - Possible Roofing Project. I was able to determine the age of the roofs and there was ample evidence that these were nearing end of life. (c) N. Retzke 2010-2021 |
Replacement Fund (reserves) Allocations - 2002-2011
Allocation of owner fees to the Replacement Fund, 2002-2018 |
The average owner's monthly fees, 2008-2014 |
The average owner's monthly fees, 2008-2018 |
The increases in the average owner's fees actually moderated after 2008 |
In this graph, the reserve expenditures decrease as the roofing project. the replacement of Lakecliffe and streams are repaired |
In this graph, reserve balances are compared using two different funding and expenditure scenarios. Other scenarios filled the gap. |
Average unit selling prices, 2009-2018 |
- Units sold 2004: 21
- 2005: 29
- 2006: 23
- 2007: 26
- 2008: 18
- 2009: 11
- 2010: 9
- 2011: 16
- 2012: 10
- 2013: 12
- 2014: 16
- 2015: 17
- 2016: 30
- 2017: 25
Notes:
1. Click for the link to the earlier post: the-replacement-fund-and-owner-fees.html
2. The Illinois Condominium Act (ILCA) does have stipulations about reserves. They are to be used "for capital expenditures and deferred maintenance for repair or replacement of the common elements." In other words, the replacement fund should not be used for whimsical, capricious projects that embellish and expand the maintenance costs and owner fees, or move beyond the existing architecture. Maintenance and embellishment are very different. The board is only empowered to maintain the association.
3. The Illinois Condominium Act provides stipulations to boards regarding budgets and reserves. The ILCA includes considerations to be give by boards when considering budgets. Regarding the Replacement Fund the ILCA stipulates that the board determined reserves are to be reasonable and the board is to consider "(iv) the financial impact on unit owners, and the market value of the condominium units, of any assessment increase needed to fund reserves; and (v) the ability of the association to obtain financing or refinancing." (emphasis mine):
(765 ILCS 605/9)
(from Ch. 30, par. 309)
Sec. 9.
Sharing of expenses - Lien for nonpayment.
2) All budgets adopted by a board of managers on or | ||
|
4. Newsletters. Recent boards have removed the BLMH.org website and the links to the earlier Newsletters contained in that website. I did post links to most of the newsletters 2008-2018 in this blog. Currently, owners can access a limited number of recent newsletters via the Association online portal.
(C) 2021 N. Retzke
No comments:
Post a Comment
Please leave a comment!
Note: Only a member of this blog may post a comment.